CQM C EXAM REVIEW UPDATED COMPLETE
QUESTIONS AND ANSWERS GRADED A+
◉ The purpose of Construction Quality Management is to: Answer:
Achieve the quality established by properly developed requirements
through the combined responsibility, but seperate efforts of contractpr
smd government personnel.
◉ Construction Quality Management is the performance of tasks,
which ensure that construction is performed. Answer: According to
plans and specifications, on time, within a defined budget and a safe
work environment.
◉ Partnering relationships are based upon: Answer: Building trust and
dedication to common goals
◉ It is the responsibility of Quality Assurance Personnel to: Answer:
Periodically verify that the contractors system of control is working
effectively.
◉ An effective contractor quality control program will: Answer: Be
an incentive for work to be done correctly the first time resulting in
earlier completion, reduced field overhead costs, and greater profits.
, ◉ The success or failure of all contractors is based upon: Answer: The
ability to control costs, finance work, estimate jobs, schedule the
work, and maintain effective quality control.
◉ Quality Assurance Personnel have the responsibility to: Answer:
Require contractors to maintain the quality specified in the plans and
specifications.
◉ Inspection is: Answer: The process by which ongoing and
completed work is examined
◉ During the punch-out inspection of a project: Answer: Quality
Assurance Personnel must assure that the contractor prepares a punch-
list and makes corrections.
◉ If there is a disagreement whether the contractors work complies
with the contract: Answer: The government makes the final
determination
◉ Characteristics that describe a definable feature of work include:
Answer: Cross-referenced listings to the contractors construction
schedule that may have more than one definable feature under a
section of the specifications.
◉ The _____________________ consists of daily checks of the work
to assure continuing compliance with contract requirements. Answer:
Follow-up phase
QUESTIONS AND ANSWERS GRADED A+
◉ The purpose of Construction Quality Management is to: Answer:
Achieve the quality established by properly developed requirements
through the combined responsibility, but seperate efforts of contractpr
smd government personnel.
◉ Construction Quality Management is the performance of tasks,
which ensure that construction is performed. Answer: According to
plans and specifications, on time, within a defined budget and a safe
work environment.
◉ Partnering relationships are based upon: Answer: Building trust and
dedication to common goals
◉ It is the responsibility of Quality Assurance Personnel to: Answer:
Periodically verify that the contractors system of control is working
effectively.
◉ An effective contractor quality control program will: Answer: Be
an incentive for work to be done correctly the first time resulting in
earlier completion, reduced field overhead costs, and greater profits.
, ◉ The success or failure of all contractors is based upon: Answer: The
ability to control costs, finance work, estimate jobs, schedule the
work, and maintain effective quality control.
◉ Quality Assurance Personnel have the responsibility to: Answer:
Require contractors to maintain the quality specified in the plans and
specifications.
◉ Inspection is: Answer: The process by which ongoing and
completed work is examined
◉ During the punch-out inspection of a project: Answer: Quality
Assurance Personnel must assure that the contractor prepares a punch-
list and makes corrections.
◉ If there is a disagreement whether the contractors work complies
with the contract: Answer: The government makes the final
determination
◉ Characteristics that describe a definable feature of work include:
Answer: Cross-referenced listings to the contractors construction
schedule that may have more than one definable feature under a
section of the specifications.
◉ The _____________________ consists of daily checks of the work
to assure continuing compliance with contract requirements. Answer:
Follow-up phase