Exam Questions and Answers |
Already Graded A+
The process of forecasting or approximating the time and cost of
completing project deliverables is called
A. Budgeting
B. Predicting
C. Estimating
D. Planning
E. Guesstimating - ANSWER ✔✔Estimating
In practice, estimating processes are frequently classified as
,A. Top down/bottom up
B. Rough/polished
C. Precise/order of magnitude
D. Draft/final
E. Both A and B are correct - ANSWER ✔✔Top down/bottom up
A typical statement in actual practice is that estimates should have a
probability of being met ______ of the time.
A. 100%
B. 98%
C. 95%
D. 90%
E. 80% - ANSWER ✔✔95%
A good starting point for developing time and cost estimates is
A. Past experience
B. Work packages
C. Task analysis
D. Time and motion studies
, E. Work breakdown structure - ANSWER ✔✔Past experience
Which of the following is not one of the factors that need to be
considered to improve quality of estimates for project times and costs?
A. Planning horizon
B. People
C. Padding estimates
D. Profit
E. Project structure - ANSWER ✔✔Profit
Ed is looking over the actual results of projects and comparing them to
what was estimated. He notices that projects that took six months or
longer to complete were noticeably more off the estimates. Which of the
following factors is he recognizing?
A. Padding estimates
B. Planning horizon
C. Project structure
D. People
E. Organization culture - ANSWER ✔✔Planning horizon