, What is NYC Chapter 33? Ch 33 = Safeguards During Construction or Demoltion
What is Section 3301 and 3302? 3301 = General
3302 = Definitions
What do you do when code does not specifically state [3301.4.1]
inspection is needed on an equipment? Any equipment (except hand tools) that affects safety of public or property shall
be inspected by a COMPETENT PERSON designated by the contractor using
the equipment
This inspection shall be documented in an inspection checklist signed and dated
by the CP
Who is responsible for maintaining construction/demo [3301.9]
signs? The permit holder for the construction/demo work
If no active permits, then the building owner
Name the (8) items that need to be listed on a Project [3301.9.1]
Information Panel 1. Rendering, elevation drawing, or zoning diagram
2. "Work in Progress" Title and specifying zoning use
3. Anticipated project completion date
4. Property owner's corporate name, address, phone #
5. Website address or phone # to contact
6. GC name and phone #
7. "To anonymously report unsafe conditions..call 311" in English and Spanish
8. Primary project permit (laminated)
Where should the Project Information Panel be posted? [3301.9.1.2]
How high up? On the fence on each perimeter
-if the perimeter is greater than 150ft, post at each corner
- posted 4ft high from the ground to the bottom edge of the panel
Name the specs of the Project Information Panel and the [3301.9.1.4]
(2) exceptions 6 ft wide x 4 ft high
Exceptions:
1) for demo project = 2'-4" wide x 4ft high
2) Sites that have street frontage less than 60 ft = 55" wide x 36.5" high
What contents should be on the SWS parapet info [3301.9.2.1]
panel? (3) 1) Street address of the site
2) Name of contractor responsible for site...if not, then the owner
3) The statement "For more info, visit NYC.GOV/BUILDINGS"
Name the (4) requirements of posting SWS parapet info [3301.9.2.2]
panel 1) Posted along the long axis of the SWS
2) Shall not be posted above/below parapet
3) Between 3-6 feet from the left edge SWS or property line
4) Centered above project info panel on Fence
What dimension shall the SWS parapet info panel be? [3301.9.2.4]
3 ft high x 6 ft wide
When do you need site safety orientation and refresher? [3301.11]
- Orientation needed for each worker at any site that requires
SSM/SSC/superintendent
- Refresher is needed after (1) year for each worker still working at the same site
Who can conduct the site safety orientation and [3301.11.3]
refresher? A qualified person designated by the permit holder
This qualified person shall have ability to communicate with each worker
What contents should be included in site safety [3301.11.4]
orientation and refresher? 1) A review of safety procedures and any hazardous activities to be performed at
the site
2) Information pertaining to site safety training SST as required in Section 3321