Incorrect 0/2.5 Points 1 Based on Scenario Part 1, answer the following six questions (questions 1 to 6): 1. Rather than wait for the next President’s Budget to obtain authorization and funding to begin work, what kind of reprogramming action must DoD pursue to obtain funding for this New Start? Scenario Part I. You are taking over as the new Program Manager (PM) assigned to a joint (and potentially international) major defense acquisition program. The program is designing, developing, and integrating a system of systems. The Milestone Decision Authority (MDA) recently approved the Material Development Decision (MDD) authorizing entry into the Materiel Solutions Analysis (MSA) Phase. In addition to the MDD, other required documentation (e.g., validated Initial Capabilities Document) was generated from the Joint Capabilities Integration and Development System (JCIDS). The MDA designated the Navy as the lead service. The program is a New Start; it has not yet been addressed in a President’s Budget Request, but based on initial cost estimates, it is expected to be designated an Acquisition Category (ACAT) I program. The program will use advanced technology and an incremental acquisition strategy, with at least one additional increment planned after this initial increment. Reprogramming Transfer Authority Congressional Prior Approval Reprogramming Internal reprogramming (IR) Below Threshold Reprogramming (BTR) Correct 2.5/2.5 Points 2 You must program for out-year funding in the Planning, Programming, Budgeting, and Execution (PPBE) decision support system. What document is used to request funding from the Office of the Secretary of Defense (OSD) through the Lead Service as part of the Programming Phase? Scenario Part I. You are taking over as the new Program Manager (PM) assigned to a joint (and potentially international) major defense acquisition program. The program is designing, developing, and integrating a system of systems. The Milestone Decision Authority (MDA) recently approved the Material Development Decision (MDD) authorizing entry into the Materiel Solutions Analysis (MSA) Phase. In addition to the MDD, other required documentation (e.g., validated Initial Capabilities Document) was generated from the Joint Capabilities Integration and Development System (JCIDS). The MDA designated the Navy as the lead service. The program is a New Start; it has not yet been addressed in a President’s Budget Request, but based on initial cost estimates, it is expected to be designated an Acquisition Category (ACAT) I program. The program will use advanced technology and an incremental acquisition strategy, with at least one additional increment planned after this initial increment. Defense Planning Guidance (DPG) Program Objective Memorandum (POM) President’s Budget Request Acquisition Strategy Correct 2.5/2.5 Points 3 You anticipate using advanced technology in an airborne environment as part of the system solution. While many of the technologies are in use in other operational systems, at least one signal processing technology works well in a factory mock-up, but has never been demonstrated in an airborne environment. You know that new technology must be demonstrated in a relevant environment prior to which of the following? Scenario Part I. You are taking over as the new Program Manager (PM) assigned to a joint (and potentially international) major defense acquisition program. The program is designing, developing, and integrating a system of systems. The Milestone Decision Authority (MDA) recently approved the Material Development Decision (MDD) authorizing entry into the Materiel Solutions Analysis (MSA) Phase. In addition to the MDD, other required documentation (e.g., validated Initial Capabilities Document) was generated from the Joint Capabilities Integration and Development System (JCIDS). The MDA designated the Navy as the lead service. The program is a New Start; it has not yet been addressed in a President’s Budget Request, but based on initial cost estimates, it is expected to be designated an Acquisition Category (ACAT) I program. The program will use advanced technology and an incremental acquisition strategy, with at least one additional increment planned after this initial increment. System Requirements Review (SRR) Milestone C Preliminary Design Review (PDR) Milestone B Incorrect 0/2.5 Points 4 You want to get work efforts moving forward to begin planning the program. In accordance with the Major Capability Acquisition pathway, at what point does the Program Management Office (PMO) need to be established? Scenario Part I. You are taking over as the new Program Manager (PM) assigned to a joint (and potentially international) major defense acquisition program. The program is designing, developing, and integrating a system of systems. The Milestone Decision Authority (MDA) recently approved the Material Development Decision (MDD) authorizing entry into the Materiel Solutions Analysis (MSA) Phase. In addition to the MDD, other required documentation (e.g., validated Initial Capabilities Document) was generated from the Joint Capabilities Integration and Development System (JCIDS). The MDA designated the Navy as the lead service. The program is a New Start; it has not yet been addressed in a President’s Budget Request, but based on initial cost estimates, it is expected to be designated an Acquisition Category (ACAT) I program. The program will use advanced technology and an incremental acquisition strategy, with at least one additional increment planned after this initial increment. Concurrent with the Capabilities Based Assessment (CBA) Once the Capability Development Document (CDD) is validated Just prior to program initiation, typically Milestone B Prior to Milestone A Correct 2.5/2.5 Points

Mostrar más Leer menos
Institución
PMT 3600V
Grado
PMT 3600V

Vista previa del contenido

PMT 3600V

Incorrect
0/2.5 Points
1
Based on Scenario Part 1, answer the following six questions (questions 1 to 6):

1. Rather than wait for the next President’s Budget to obtain authorization
and funding to begin work, what kind of reprogramming action must DoD
pursue to obtain funding for this New Start?
Scenario Part I. You are taking over as the new Program Manager (PM) assigned to a
joint (and potentially
international) major defense acquisition program. The program is designing,
developing, and
integrating a system of systems. The Milestone Decision Authority (MDA) recently
approved the
Material Development Decision (MDD) authorizing entry into the Materiel Solutions
Analysis (MSA)
Phase. In addition to the MDD, other required documentation (e.g., validated Initial
Capabilities
Document) was generated from the Joint Capabilities Integration and Development
System (JCIDS). The MDA designated the Navy as the lead service. The program is a
New Start; it has not yet been addressed in a President’s Budget Request, but based on
initial cost estimates, it is expected to be designated an Acquisition Category (ACAT) I
program. The program will use advanced technology and an incremental acquisition
strategy, with at least one additional increment planned after this initial increment.



Reprogramming Transfer Authority
Congressional Prior Approval Reprogramming
Internal reprogramming (IR)
Below Threshold Reprogramming (BTR)
Correct
2.5/2.5 Points
2
You must program for out-year funding in the Planning, Programming,
Budgeting, and Execution (PPBE) decision support system. What document is
used to request funding from the Office of the Secretary of Defense (OSD)
through the Lead Service as part of the Programming Phase?
Scenario Part I. You are taking over as the new Program Manager (PM) assigned to a
joint (and potentially
international) major defense acquisition program. The program is designing,
developing, and
integrating a system of systems. The Milestone Decision Authority (MDA) recently
approved the
Material Development Decision (MDD) authorizing entry into the Materiel Solutions
Analysis (MSA)
Phase. In addition to the MDD, other required documentation (e.g., validated Initial
Capabilities
Document) was generated from the Joint Capabilities Integration and Development

, System (JCIDS). The MDA designated the Navy as the lead service. The program is a
New Start; it has not yet been addressed in a President’s Budget Request, but based on
initial cost estimates, it is expected to be designated an Acquisition Category (ACAT) I
program. The program will use advanced technology and an incremental acquisition
strategy, with at least one additional increment planned after this initial increment.



Defense Planning Guidance (DPG)
Program Objective Memorandum (POM)
President’s Budget Request
Acquisition Strategy
Correct
2.5/2.5 Points
3
You anticipate using advanced technology in an airborne environment as part
of the system solution. While many of the technologies are in use in other
operational systems, at least one signal processing technology works well in a
factory mock-up, but has never been demonstrated in an airborne
environment.

You know that new technology must be demonstrated in a relevant
environment prior to which of the following?
Scenario Part I. You are taking over as the new Program Manager (PM) assigned to a
joint (and potentially
international) major defense acquisition program. The program is designing,
developing, and
integrating a system of systems. The Milestone Decision Authority (MDA) recently
approved the
Material Development Decision (MDD) authorizing entry into the Materiel Solutions
Analysis (MSA)
Phase. In addition to the MDD, other required documentation (e.g., validated Initial
Capabilities
Document) was generated from the Joint Capabilities Integration and Development
System (JCIDS). The MDA designated the Navy as the lead service. The program is a
New Start; it has not yet been addressed in a President’s Budget Request, but based on
initial cost estimates, it is expected to be designated an Acquisition Category (ACAT) I
program. The program will use advanced technology and an incremental acquisition
strategy, with at least one additional increment planned after this initial increment.

Escuela, estudio y materia

Institución
PMT 3600V
Grado
PMT 3600V

Información del documento

Subido en
24 de julio de 2026
Número de páginas
13
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

$13.99
Accede al documento completo:

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Brainarium Delaware State University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1969
Miembro desde
3 año
Número de seguidores
1045
Documentos
23685
Última venta
5 horas hace

3.8

333 reseñas

5
155
4
63
3
57
2
16
1
42

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes