, The right to repossess or replevy unused materials from True.
a jobsite will not be effective if someone, in good faith,
purchased it after removal from the site of the
improvement.
The contractor must within _____ days after the receipt 10 days.
of the property owner's request, furnishish to property
owner or the property owner's agent a list of the
subcontractors and suppliers who have a contract with
the contractor as of the date the request is received by
the contractor.
A property perfected lien may be discharged by an order county
of the circuit court of the _____ where the property is
located.
When any interested party files a complaint, the clerk will 20 days
issue a summons to the lienor to show cause within
_____ days why his or her lien should not to be enforced
by action or vacated and canceled of record.
If a lienor fails to show cause why his or her lien should True
not be enforced or fails to start such action before the
return date of the summons, the court will immediately
order cancellation of the lien.
No lien provided by part 713.22 will continue for longer 1 year
then ____ years after the claim of lien has been
recorded.
No lien provided by part 713.22 will continue for no 1 year
longer then _______ years after the recording of an
amended claim of lien that shows a later date of final
furnishing of labor, services, or materials.
The lien of any lienor upon whom Notice of contest of 60
Lien is served and who fails to institute a suit to enforce
his or her lien within ________ days after service of such
notice will be extinguished automatically.
The payment bond is required to ______ an owner under exempt
s. 713.23 must be furnished by the contractor in at least
the amount of the original contract price before
commencing the construction of the improvement under
the direct contract.
A copy the payment bond must be attached to the Notice recorded
of Commencement when it is _______.
Anyone who willfully files a fraudulent lien as defined in third
713.31 commits a felony of the ______ degree
When a construction project is "put out" for bid, the The contractor
contractors are given the plans and specifications for the
project. If any deviations for these specifications occur,
who will be held responsible and may be required to
correct them at their own expense?
The ______ for a protect are interpreted as a legal specifications
document that specifically defines the responsibilities of
the owner and his representatives intended for the
project and what the contractors responsibilities are.
The CSI-MASTERFORMAT divides the specifications 50
into __________ specific divisions to provide a standard
reference and filing numbers for bidding and contract
forms.