Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 2 fuera de 7 páginas
Examen

Latest Florida electrical business exam with correct answers 2026/2027 version A+ Graded

Document preview thumbnail
Vista previa 2 fuera de 7 páginas

Latest Florida electrical business exam with correct answers 2026/2027 version A+ Graded

Vista previa del contenido

Latest Florida electrical business exam with correct answers
2026/2027 version A+ Graded

If a lienor fails to show cause why his or her lien should not be enforced or fails to start
such action before the return date of the summons, the court will immediately order
cancellation of the lien. - correct answer >>>True

No lien provided by part 713.22 will continue for longer then ____ years after the claim
of lien has been recorded. - correct answer >>>1 year

No lien provided by part 713.22 will continue for no longer then _______ years after the
recording of an amended claim of lien that shows a later date of final furnishing of labor,
services, or materials. - correct answer >>>1 year

The lien of any lienor upon whom Notice of contest of Lien is served and who fails to
institute a suit to enforce his or her lien within ________ days after service of such
notice will be extinguished automatically. - correct answer >>>60

The payment bond is required to ______ an owner under s. 713.23 must be furnished
by the contractor in at least the amount of the original contract price before commencing
the construction of the improvement under the direct contract. - correct answer
>>>exempt

A copy the payment bond must be attached to the Notice of Commencement when it is
_______. - correct answer >>>recorded

Anyone who willfully files a fraudulent lien as defined in 713.31 commits a felony of the
______ degree - correct answer >>>third

When a construction project is "put out" for bid, the contractors are given the plans and
specifications for the project. If any deviations for these specifications occur, who will be
held responsible and may be required to correct them at their own expense? - correct
answer >>>The contractor

The ______ for a protect are interpreted as a legal document that specifically defines
the responsibilities of the owner and his representatives intended for the project and
what the contractors responsibilities are. - correct answer >>>specifications

The CSI-MASTERFORMAT divides the specifications into __________ specific
divisions to provide a standard reference and filing numbers for bidding and contract
forms. - correct answer >>>50

Which of the following would appear as a heading in the index of the General Clauses
and Conditions sections of General Requirements? - correct answer >>>All of these (
General Conditions, Notice to Bidders and Proposal)

, _________ is the contractors price for performing the work as specified. - correct
answer >>>The proposal

"Contract Documents" "Insurance," "payments," and "Guarantee" are some typical items
that would be included under what heading in the General Clauses and Conditions
section? - correct answer >>>General Conditions

The square footage method of estimating is always recommended for lump-sum
contracts. - correct answer >>>False

The typical _______ provides the necessary control devices for the accumulation of
estimates into the final bid. - correct answer >>>Estimate summary sheet

What type of estimate is an accurate estimating method that consists of listing all
material and labor needed for an element of work or project - correct answer
>>>Detailed Survey

_________ estimates are used as a check to determine if sufficient materials are
available to construct or complete a project. - correct answer >>>Material

Which of the following are types of labor estimates?
I. Preliminary manpower estimates
II. Detailed manpower estimates
III.Production manpower estimates - correct answer >>>I and II only

The satisfactory completion of the work for the stand number of dollars in a lump-sum
contract remains the obligation of the contractor regardless of the troubles that may be
experienced in the course of construction activities. - correct answer >>>True

The summary account can be updated on a ________ basis. - correct answer >>>All of
these ( monthly, weekly, daily)

Responsibility for job progress typically lies with ________. - correct answer >>>the
project engineer

The right to repossess or replevy unused materials from a jobsite will not be effective if
someone, in good faith, purchased it after removal from the site of the improvement. -
correct answer >>>True.

The contractor must within _____ days after the receipt of the property owner's request,
furnishish to property owner or the property owner's agent a list of the subcontractors
and suppliers who have a contract with the contractor as of the date the request is
received by the contractor. - correct answer >>>10 days.

Información del documento

Subido en
23 de julio de 2026
Número de páginas
7
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$21.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Ihuman
4.6
(85)
Vendido
34
Seguidores
10
Artículos
544
Última venta
4 días hace


Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes