Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 2 fuera de 8 páginas
Examen

CHAPTER 9: PROJECT SCHEDULING: PERT/CPM QUESTIONS AND VERIFIED DETAILED SOLUTIONS ( MULTIPLE CHOICES) |100% CORRECT!! ALREADY GRADED A+

Document preview thumbnail
Vista previa 2 fuera de 8 páginas

CHAPTER 9: PROJECT SCHEDULING: PERT/CPM QUESTIONS AND VERIFIED DETAILED SOLUTIONS ( MULTIPLE CHOICES) |100% CORRECT!! ALREADY GRADED A+

Vista previa del contenido

CHAPTER 9: PROJECT SCHEDULING: PERT/CPM QUESTIONS AND
VERIFIED DETAILED SOLUTIONS ( MULTIPLE CHOICES) |100%
CORRECT!! ALREADY GRADED A+



Critical activities are those that can be delayed without delaying the entire project. (T/F) -
(ANSWER)FALSE



PERT and CPM are applicable only when there is no dependence among activities. (T/F) -
(ANSWER)FALSE



A path through a project network must reach every node. (T/F) - (ANSWER)FALSE



A critical activity can be part of a noncritical path. (T/F) - (ANSWER)TRUE



When activity times are uncertain, an activity's most likely time is the same as its expected time. (T/F) -
(ANSWER)FALSE



The earliest finish time for the final activity is the project duration. (T/F) - (ANSWER)TRUE



The length of time an activity can be delayed without affecting the project completion is the slack. (T/F) -
(ANSWER)TRUE



When activity times are uncertain, total project time is normally distributed with mean equal the sum of
the means of all of the critical activities. (T/F) - (ANSWER)TRUE



Crashing refers to an unanticipated delay in a critical path activity that causes the total time to exceed its
limit. (T/F) - (ANSWER)FALSE



Constraints in the LP models for crashing decisions are required to compare the activity's earliest finish
time with the earliest finish time of each predecessor. (T/F) - (ANSWER)TRUE



The project manager should monitor the progress of any activity with a large time variance even if the
expected time does not identify the activity as a critical activity. (T/F) - (ANSWER)TRUE

, CHAPTER 9: PROJECT SCHEDULING: PERT/CPM QUESTIONS AND
VERIFIED DETAILED SOLUTIONS ( MULTIPLE CHOICES) |100%
CORRECT!! ALREADY GRADED A+




The variance in the project completion time is the sum of the variances of all activities in the project.
(T/F) - (ANSWER)FALSE



The latest finish time for an activity is the largest of the latest start times for all activities that
immediately follow the activity. (T/F) - (ANSWER)FALSE



The earliest start time for an activity is equal to the smallest of the earliest finish times for all its
immediate predecessors. (T/F) - (ANSWER)FALSE



The linear programming model for crashing presented in the textbook assumes that any portion of the
activity crash time can be achieved for a corresponding portion of the activity crashing cost. (T/F) -
(ANSWER)TRUE



All activities on a critical path have zero slack time. (T/F) - (ANSWER)TRUE



The difference between an activity's earliest finish time and the latest finish time equals the difference
between its earliest time and latest start time. (T/F) - (ANSWER)TRUE



It is possible to have more than one critical path at a time. (T/F) - (ANSWER)TRUE



Activities require time to complete while events do not. (T/F) - (ANSWER)TRUE



Precedence relationships among activities is critical in CPM analysis but not in PERT. (T/F) -
(ANSWER)FALSE



The normal distribution tends to be a better approximation of the distribution of total time for shorter
projects where the critical path has relatively few activities. (T/F) - (ANSWER)FALSE

Información del documento

Subido en
23 de julio de 2026
Número de páginas
8
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
Gratis
Descarga

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Vendido
2
Seguidores
0
Artículos
360
Última venta
1 día hace


Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes