The project scope planning processes include all of the following EXCEPT:
a. how the project scope will be defined
b. how the requirements will be collected
c. how the work breakdown structure will be created
d. how the business case will be created
d. how the business case will be created
Define Scope is the process of developing:
a. a project scope management plan.
b. a detailed description of the project and product.
c. a project work breakdown structure.
d. a project scope network diagram
b. a detailed description of the project and product.
All of the following elements should be included in a project scope
statement EXCEPT:
a. project boundaries or exclusions
b. names of the project team members
, c. assumptions and constraints that may limit or influence project work
d. key deliverables with acceptance criteria
b. names of the project team members
On agile projects, the scope definition begins with :
a. brainstorming
b. joint application development (JAD) sessions
c. creation of the WBS
d. user stories
d. user stories
It is helpful to list requirements and supporting information in a
requirements traceability matrix. When requirements are complete, they
should meet all of these criteria EXCEPT:
a. identified with the stakeholder who needs it
b. assigned to a team member who will be the requirement owner
c. measurable, so that the value and completion can be verified
d. prioritized so tradeoff decisions can be made if necessary
b. assigned to a team member who will be the requirement owner
Answers
The project scope planning processes include all of the following EXCEPT:
a. how the project scope will be defined
b. how the requirements will be collected
c. how the work breakdown structure will be created
d. how the business case will be created
d. how the business case will be created
Define Scope is the process of developing:
a. a project scope management plan.
b. a detailed description of the project and product.
c. a project work breakdown structure.
d. a project scope network diagram
b. a detailed description of the project and product.
All of the following elements should be included in a project scope
statement EXCEPT:
a. project boundaries or exclusions
b. names of the project team members
, c. assumptions and constraints that may limit or influence project work
d. key deliverables with acceptance criteria
b. names of the project team members
On agile projects, the scope definition begins with :
a. brainstorming
b. joint application development (JAD) sessions
c. creation of the WBS
d. user stories
d. user stories
It is helpful to list requirements and supporting information in a
requirements traceability matrix. When requirements are complete, they
should meet all of these criteria EXCEPT:
a. identified with the stakeholder who needs it
b. assigned to a team member who will be the requirement owner
c. measurable, so that the value and completion can be verified
d. prioritized so tradeoff decisions can be made if necessary
b. assigned to a team member who will be the requirement owner