Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 2 fuera de 13 páginas
Examen

PMP Practice Exam Questions with correct answers and rationales graded a+ for 2026

Document preview thumbnail
Vista previa 2 fuera de 13 páginas

PMP Practice Exam Questions with correct answers and rationales graded a+ for 2026

Vista previa del contenido

PMP Practice Exam Questions with
correct answers and rationales graded
a+ for 2026
Question 1: During which of the following project development life cycles are the project
scope, schedule, and budget determined in the early phases of the life cycle?

Correct Answer:
Predictive Life Cycle

Rationale:
In a Predictive Life Cycle, the project scope, schedule, and budget are defined early during
project planning. The project follows a detailed plan, and changes are managed through formal
change control procedures.

Exam Tip:
Predictive = Plan-driven approach
Scope, cost, and schedule are determined early.



Question 2: Which of the following is the correct definition of a project management
methodology?

Correct Answer:
System of practices, techniques, rules, and procedures used by those who work in a discipline

Rationale:
A project management methodology provides a structured framework containing processes,
practices, tools, techniques, and procedures that guide project teams in managing projects
effectively.



Question 3: You have recommended developing a business case for each organizational
project followed by development of a project benefits management plan. Who would you
recommend to be the owner of the business case?

, Correct Answer:
Project Sponsor

Rationale:
The project sponsor is accountable for developing and maintaining the business case. The
sponsor ensures that the project remains aligned with organizational strategy and delivers
expected benefits.

Exam Tip:
Sponsor owns the Business Case.
Project Manager owns project execution.



Question 4: The finance department approves a number of capital projects annually. You are
responsible for constructing a new manufacturing facility requiring a plant, warehouses, and
storage and distribution locations. Your role at this organization is:

Correct Answer:
Program Manager

Rationale:
A program consists of multiple related projects managed together to achieve benefits that
would not be achieved if managed separately. The construction activities represent several
related projects under one larger program.



Question 5: You have been hired by a startup to develop its process architecture and define its
operating model. The operating model will be used by the business to manage day-to-day
operations. Your engagement is an example of:

Correct Answer:
Project

Rationale:
This work has a defined beginning and end, making it a temporary endeavor. Although the
operating model will later support operations, creating it is a project.



Questionu6:uWhichuofutheufollowingustatementsuregardinguProjectuManagementuBodyuofuKnowl
edgeu(PMBOK®)uisuincorrect?

Información del documento

Subido en
18 de julio de 2026
Número de páginas
13
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$16.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Vendido
23
Seguidores
3
Artículos
2162
Última venta
3 semanas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes