Florida Contractor's Manual Exam | Verified Exam Questions and
Answers | Latest Updated Study Material 2026
Question:
A Subcontractor's employee incorrectly performs the Work. Who is responsible (to the Owner)
for the error?
1- Subcontractor employee
2- Architect
3- Subcontractor
4- Contractor
Answer:
A201: 3.3.2
Question:
Article 3) Contractor
3.3 Supervision and Construction Procedures
4- Contractor
Which of the following is NOT a cause for the Owner to terminate the Contract?
1- The Contractor experiences delays due to a Stop Work order through an act of government
2- The Contractor fails to make payment to Subcontractors for labor
3- The Contractor is guilty of substantial breach of a provision of the Contract Documents
4- The Contractor repeatedly fails to supply enough properly skilled workers
Answer:
A201: 14.2.1
Question:
Article 14) Termination or Suspension of the Contract
14.2 Termination by the Owner for Cause
1- The Contractor experiences delays due to a Stop Work order through an act of government
Which of the following is owner of all drawings and specifications?
1- Contractor
2- Owner
,3- Architect
4- Supplier
Answer:
A201: 1.5.1
Question:
Article 1) General Provisions
1.5 Ownership and Use of Drawings, Specifications and Other Instruments of Service
3- Architect
Except for those Claims excluded by this AIA A201 Section 15,2,1, an initial decision shall be
required as a condition precedent to mediation of any Claim arising prior to the date final
payment is due, unless 30 days have passed after the Claim has been referred to the Initial
Decision Maker with no decision having been rendered.
1- 10
2- 20
3- 15
4- 30
Answer:
A201: 15.2.1
Question:
Article 15) Claims and Disputes
15.2 Initial Decision
4- 30
The will on request furnish to a information regarding
percentages of completion or amounts applied for by the Contractor
1- Subcontractor; Owner
2- Architect; Subcontractor
3- Owner; Subcontractor
4- Owner; Architect
Answer:
A201: 9.6.3
,Question:
Article 9) Payments and Completiong
9.6 Progress Payments
2- Architect; Subcontractor
To whom is the Subcontractor bound to by the Contract Documents?
1- Architect
2- Owner
3- Themselves
4- Contractor
Answer:
A201: 5.3
Question:
Article 5) Subcontractors
5- 3 Subcontractual Relations
4- Contractor
The Initial Decision Maker will review claims within 10 days of the receipt of the Claim take
one or more of the following actions. Which of the following actions will NOT be taken?
1- Approve the Claim
2- Request additional supporting data from the Claimant
3- Reject the Claim
4- Ignore the request
Answer:
A201: 15.2.2
Question:
Article 15) Claims and Disputes
15.2 Initial Decision
4- Ignore the request
A Sub-subcontractor is a person or entity who has a direct or indirect contract with a/an
to perform a portion of the Work at the site
, 1- Contractor
2- Subcontractor
3- Architect
4- Supplier
Answer:
A201: 5.1.2
Question:
Article 5) Subcontractors
5.1 Definitions
2- Subcontractor
If the Work is stopped for a period of consecutive
days through no fault of the Contractor, or Subcontractor, agents, employees or any other persons
performing portions of the Work under contract with the Contractor, the Contractor may
terminate the Contract and recover from the Owner
1- 120
2- 60
3- 30
4- 45
Answer:
A201: 14.1.4
Question:
Article 14) Termination or Suspension of the Contract
14.1 Termination by the Contractor
2- 60
What is the maximum amount of time after Substantial Completion of the Work shall all claims
(by Owner and Contractor) regarding the Contract by commenced?
1- Six months
2- One year
3- Ten years
4- Five years
Answers | Latest Updated Study Material 2026
Question:
A Subcontractor's employee incorrectly performs the Work. Who is responsible (to the Owner)
for the error?
1- Subcontractor employee
2- Architect
3- Subcontractor
4- Contractor
Answer:
A201: 3.3.2
Question:
Article 3) Contractor
3.3 Supervision and Construction Procedures
4- Contractor
Which of the following is NOT a cause for the Owner to terminate the Contract?
1- The Contractor experiences delays due to a Stop Work order through an act of government
2- The Contractor fails to make payment to Subcontractors for labor
3- The Contractor is guilty of substantial breach of a provision of the Contract Documents
4- The Contractor repeatedly fails to supply enough properly skilled workers
Answer:
A201: 14.2.1
Question:
Article 14) Termination or Suspension of the Contract
14.2 Termination by the Owner for Cause
1- The Contractor experiences delays due to a Stop Work order through an act of government
Which of the following is owner of all drawings and specifications?
1- Contractor
2- Owner
,3- Architect
4- Supplier
Answer:
A201: 1.5.1
Question:
Article 1) General Provisions
1.5 Ownership and Use of Drawings, Specifications and Other Instruments of Service
3- Architect
Except for those Claims excluded by this AIA A201 Section 15,2,1, an initial decision shall be
required as a condition precedent to mediation of any Claim arising prior to the date final
payment is due, unless 30 days have passed after the Claim has been referred to the Initial
Decision Maker with no decision having been rendered.
1- 10
2- 20
3- 15
4- 30
Answer:
A201: 15.2.1
Question:
Article 15) Claims and Disputes
15.2 Initial Decision
4- 30
The will on request furnish to a information regarding
percentages of completion or amounts applied for by the Contractor
1- Subcontractor; Owner
2- Architect; Subcontractor
3- Owner; Subcontractor
4- Owner; Architect
Answer:
A201: 9.6.3
,Question:
Article 9) Payments and Completiong
9.6 Progress Payments
2- Architect; Subcontractor
To whom is the Subcontractor bound to by the Contract Documents?
1- Architect
2- Owner
3- Themselves
4- Contractor
Answer:
A201: 5.3
Question:
Article 5) Subcontractors
5- 3 Subcontractual Relations
4- Contractor
The Initial Decision Maker will review claims within 10 days of the receipt of the Claim take
one or more of the following actions. Which of the following actions will NOT be taken?
1- Approve the Claim
2- Request additional supporting data from the Claimant
3- Reject the Claim
4- Ignore the request
Answer:
A201: 15.2.2
Question:
Article 15) Claims and Disputes
15.2 Initial Decision
4- Ignore the request
A Sub-subcontractor is a person or entity who has a direct or indirect contract with a/an
to perform a portion of the Work at the site
, 1- Contractor
2- Subcontractor
3- Architect
4- Supplier
Answer:
A201: 5.1.2
Question:
Article 5) Subcontractors
5.1 Definitions
2- Subcontractor
If the Work is stopped for a period of consecutive
days through no fault of the Contractor, or Subcontractor, agents, employees or any other persons
performing portions of the Work under contract with the Contractor, the Contractor may
terminate the Contract and recover from the Owner
1- 120
2- 60
3- 30
4- 45
Answer:
A201: 14.1.4
Question:
Article 14) Termination or Suspension of the Contract
14.1 Termination by the Contractor
2- 60
What is the maximum amount of time after Substantial Completion of the Work shall all claims
(by Owner and Contractor) regarding the Contract by commenced?
1- Six months
2- One year
3- Ten years
4- Five years