1. Which project management process group focuses primarily on
defining a new project or phase?
A. Monitoring and Controlling
B. Executing
C. Closing
D. Initiating
Rationale: The Initiating process group establishes the project charter,
identifies stakeholders, and formally authorizes the project or phase.
2. What is the primary purpose of a project charter?
,A. To create the project schedule
B. To assign team salaries
C. To formally authorize the project
D. To close procurement contracts
Rationale: A project charter officially authorizes the existence of the
project and gives the project manager authority to use organizational
resources.
3. Which document defines how the project is executed, monitored, and
controlled?
A. Risk Register
B. Stakeholder Register
C. Project Management Plan
D. Scope Statement
Rationale: The Project Management Plan integrates all subsidiary plans
and baselines for managing the project.
4. A project manager is using lessons learned from previous projects to
improve efficiency. What organizational process asset is being used?
A. Enterprise Environmental Factors
B. Change Requests
,C. Lessons Learned Repository
D. Project Scope Baseline
Rationale: Lessons learned repositories are organizational process assets
that help teams apply historical knowledge.
5. Which knowledge area includes processes required to ensure timely
completion of the project?
A. Cost Management
B. Quality Management
C. Scope Management
D. Schedule Management
Rationale: Schedule Management focuses on planning, developing, and
controlling the project timeline.
6. What is the primary output of the Define Scope process?
A. Risk Register
B. Work Breakdown Structure
C. Project Scope Statement
D. Schedule Baseline
Rationale: The Define Scope process produces the Project Scope Statement,
detailing project deliverables and boundaries.
, 7. In a Work Breakdown Structure (WBS), the lowest level is called:
A. Control Account
B. Milestone
C. Activity List
D. Work Package
Rationale: Work packages are the smallest deliverable-oriented
components in a WBS and can be estimated and managed effectively.
8. Which estimating technique uses statistical relationships between
historical data and variables?
A. Bottom-Up Estimating
B. Analogous Estimating
C. Parametric Estimating
D. Three-Point Estimating
Rationale: Parametric estimating applies mathematical models and
historical data for cost or duration estimation.
9. What is the critical path in project management?
A. The most expensive project activity
B. The shortest sequence of tasks
C. The longest sequence of activities determining project duration
D. The path with the highest risk