◎ 5 Ds of Role Clarity. ANSWER:- 1. Discuss
2. Determine
3. Document
4. Disclose
5. Do
◎ Must disclose in writing. ANSWER:- - the nature of services provided
- whether professional has entered into representation relationship with other party
- any conflicts of interest
- any other facts that may influence consumers decision to proceed with relationship
made to clarify and provide proof of undertanding in event issues or disputes arise
◎ Written Service Agreement vs Customer Acknowledgement Forms. ANSWER:-
Written Service Agreement
- when consumer chooses a representation relationship
- becomes a client
- provide signed copy to brokerage
Customer Acknowledge forms
- non-representation relationship
- becomes a customer
- provide signed copy to brokerage
◎ PIPEDA. ANSWER:- - Federal legislation
◎ PIPA. ANSWER:- Alberta's legislation, how private organizations use and disclose
personal information.
◎ Power of Attorney. ANSWER:- a legal document authorizing someone to act on your
behalf
- must be 18
- POA must be written, dated and signed by both donor and witness
- donor must be mentally capable or contract is void
- only effective as long as donor is alive, will takes effect once death
◎ Types of POA. ANSWER:- General POA
,- has no limits on powers of the attorney
- can make all decisions regarding financial and legal affairs
- exception where the donor resides and health care
Special POA
- make certain decisions
- also called limited POA
- may grant authority to oversee sale, deals with land
- must be registered on Certificate of Title
Immediate POA
- takes effect as soon as POA is signed, dated and witnessed
- terminates upon loss of mental capacity or death
Enduring POA
- immediately upon being signed, dated and witnessed
- continues if donor becomes incapable, mentally incapacitated
- must include statement whether it takes effect immediately and continues...
◎ Judicial Sale. ANSWER:- Court ordered sale usually as a way to resolve legal
matters
- primary debt recovery method for default mortgages
◎ Foreclosure. ANSWER:- legal action supervised by the court following a default on
the mortgage.
-transfers the real property from the borrower to the lender and erases interests on title.
◎ Alberta Building Code. ANSWER:- Legislation that establishes technical
specifications for new building construction and construction materials
◎ Building Permit. ANSWER:- typically valid for one year during which construction
process must be initiated
◎ Factory Built Construction. ANSWER:- Manufactured
- three sections that are 95% complete when they leave the factory.
- secure the sections to the foundation and join together
- can often move in the same day or within days
- saves time and mony
Modular Construction
- manufacturing three dimensional units, 85 percent complete when they leave
- requires few weeks on site to be complete
- allows for creation of multi-story buildings
Panelized construction
- creation of pre-fabricated wall, floor or roof panels
, - panels may be completed fully or partially
- may consist of just the frame or fully complete with windows and siding
◎ Alberta Safety Codes Act. ANSWER:- provincial legislation that sets specifications
for new building.
◎ Components of Construction. ANSWER:- Lot
Substructure - building foundation
Superstructure - above grade construction
includes; envelope, service systems, interior
- building envelope - everything that encloses the structure
- roof, exterior walls, windows, doors, and interior walls
- building service systems - supply's essential services
- heat, electricity, water
- interior - interior walls, features, finishes, and fixtures
Pre-wired
- security systems, internet, fireplace controls, windows
◎ Preserved Wood foundation. ANSWER:- treated wood, must be certified with a
stamp.
- must be examined by engineer or architect stating conforms to the Alberta Building
Code requirements
- poured concrete is the most common foundation
◎ Subsurface Drainage. ANSWER:- Drain tiles - directs water to storm system or sump
pit
Sump Pump
- located in sump pit in the foundation, accessible
- submersible pump - installed within the sump pit
- pedestal/upright - set outside of the sump pit
◎ Parging. ANSWER:- Thin top coat that is applied to exterior finish, used to create
smooth surface. can be cement or acrylic
- protects above grade foundation walls
◎ Building Floors. ANSWER:- Beams - structural components that create base
Joist - support part of structure, placed horizontal - supports floor or ceiling
Bridging/Blocking - adds to load carrying capabilities and reduces the potential for
movement.
◎ R-Value or RSI. ANSWER:- the rate at which heat moves through insulation, the
higher the value the more effective the material is at resisting the transfer of heat.