OPRE 3330 TEST 3 QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026 (1) Cost Management - Answers The process of estimating, allocating, and controlling project cost. (1) What are some of the challenges of cost management? - Answers - Lack or resources - Poor cost estimation (1) What are the 4 types of cost? - Answers Fixed cost, variable cost, direct cost, and indirect cost. (1) Fixed cost: - Answers Cost that doesn't change as production changes. EX: rent (1) Variable cost: - Answers Cost that varies as time progresses EX: materials and supplies (1) Direct Cost: - Answers Cost that is a direct attribute to the project work EX: salary (1) Indirect cost: - Answers A cost that is not directly apart of the project EX: lighting, AC, etc. (1) What are the Cost Management processes? - Answers Plan cost management, estimate costs, determine budget, control cost. (1) A cost management plan can establish: - Answers - Units of measure - Level of precision - level of accuracy (1) What are the estimating costs? - Answers - Analogues estimating - Parametric estimating - Bottom-Up estimating - 3-Point estimating (1) Analogue Estimating: - Answers Measure that projects parameters such as budget, size, complexity, and duration based on previous projects. (1) Parametric Estimating: - Answers A mathematical model based on historical records. (1) Bottom-Up Estimating: - Answers Accurate but costly in terms of time and labor to develop. The best one. (1) 3-Point Estimating: - Answers Estimates by taking a weighted average of the 3 estimates using this formula: (0+4m+P)/6 (1) What are the values of the 3-Point estimating? - Answers - Optimistic Cost - Most Likely Cost - Pessimistic Cost (1) What is Optimistic cost? - Answers The lowest possible cost in which AB activity can be completed under perfect circumstances. (1) What is Most Likely Cost? - Answers The most likely costs under normal circumstances. (1) What is Pessimistic Cost? - Answers The highest possible cost under the worst case scenario. (1) Reserve Cost: - Answers The extra money in a project budget to be used if necessary. If the risk occurs, it is classified as either management reserve or contingency reserve. (2) Estimated Cost: - Answers The total project cost estimates that the project manager makes. (2) Budgeted Cost: - Answers A budget that the management has prepared and allocated to the project. (Shows how money is spent) (2) Cost baseline: - Answers A time-phased budget used to monitor, measure, and control cost performance during the project. - It includes Contingency Reserves but not the Management Reserves (2) Question 1: Determining Budget - Answers (2) Cost Baseline= - Answers Cost Baseline = Cost Estimate + Contingency Reserve (2) Project Budget= - Answers Project Budget = Cost Baseline + Management Reserve (2) Control Costs: - Answers The process of monitoring the status of the project to update the project costs and managing changing the cost baseline. (2) Earned Value Management (EVM): - Answers A common method of project performance and progress measurement throughout the project lifecycle in terms of the cost and schedule control. (2) EVM compares.... - Answers the budgeted and actual costs to a project (2) What are EVM's 3 Main Components? - Answers - Planned Value (PV) - Earned Value (EV) - Actual Cost (AC)

Vista previa del contenido

OPRE 3330 TEST 3 QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026

(1) Cost Management - Answers The process of estimating, allocating, and controlling project cost.
(1) What are some of the challenges of cost management? - Answers - Lack or resources
- Poor cost estimation
(1) What are the 4 types of cost? - Answers Fixed cost, variable cost, direct cost, and indirect cost.
(1) Fixed cost: - Answers Cost that doesn't change as production changes. EX: rent
(1) Variable cost: - Answers Cost that varies as time progresses EX: materials and supplies
(1) Direct Cost: - Answers Cost that is a direct attribute to the project work EX: salary
(1) Indirect cost: - Answers A cost that is not directly apart of the project EX: lighting, AC, etc.
(1) What are the Cost Management processes? - Answers Plan cost management, estimate costs,
determine budget, control cost.
(1) A cost management plan can establish: - Answers - Units of measure
- Level of precision
- level of accuracy
(1) What are the estimating costs? - Answers - Analogues estimating
- Parametric estimating
- Bottom-Up estimating
- 3-Point estimating
(1) Analogue Estimating: - Answers Measure that projects parameters such as budget, size,
complexity, and duration based on previous projects.
(1) Parametric Estimating: - Answers A mathematical model based on historical records.
(1) Bottom-Up Estimating: - Answers Accurate but costly in terms of time and labor to develop. The
best one.
(1) 3-Point Estimating: - Answers Estimates by taking a weighted average of the 3 estimates using this
formula: (0+4m+P)/6
(1) What are the values of the 3-Point estimating? - Answers - Optimistic Cost
- Most Likely Cost
- Pessimistic Cost
(1) What is Optimistic cost? - Answers The lowest possible cost in which AB activity can be completed
under perfect circumstances.
(1) What is Most Likely Cost? - Answers The most likely costs under normal circumstances.
(1) What is Pessimistic Cost? - Answers The highest possible cost under the worst case scenario.
(1) Reserve Cost: - Answers The extra money in a project budget to be used if necessary. If the risk
occurs, it is classified as either management reserve or contingency reserve.
(2) Estimated Cost: - Answers The total project cost estimates that the project manager makes.
(2) Budgeted Cost: - Answers A budget that the management has prepared and allocated to the
project. (Shows how money is spent)
(2) Cost baseline: - Answers A time-phased budget used to monitor, measure, and control cost
performance during the project.
- It includes Contingency Reserves but not the Management Reserves
(2) Question 1: Determining Budget - Answers
(2) Cost Baseline= - Answers Cost Baseline = Cost Estimate + Contingency Reserve
(2) Project Budget= - Answers Project Budget = Cost Baseline + Management Reserve
(2) Control Costs: - Answers The process of monitoring the status of the project to update the project
costs and managing changing the cost baseline.
(2) Earned Value Management (EVM): - Answers A common method of project performance and
progress measurement throughout the project lifecycle in terms of the cost and schedule control.
(2) EVM compares.... - Answers the budgeted and actual costs to a project
(2) What are EVM's 3 Main Components? - Answers - Planned Value (PV)
- Earned Value (EV)
- Actual Cost (AC)
(2) What is Planned Value? - Answers How far along a project should take.
(2) What is Earned Value? - Answers The work that has actually been performed to date.
(2) What is Actual Cost? - Answers The sum of money spent so far.
(2) Budget at Completion (BAC): - Answers The total budget allocated to the project.
(2) Actual cost is used to calculate...... - Answers Cost variance (CV) and the Cost performance Index.

Información del documento

Subido en
13 de julio de 2026
Número de páginas
2
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$11.79

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
joshuawesonga22
3.4
(12)
Vendido
114
Seguidores
2
Artículos
14877
Última venta
1 día hace


Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes