Inspection and acceptance criteria for fixed-price deliver-
ables include:
Under a cost-reimbursement, time and materials, or labor
The COR should notify the contractor immediately if there
hour contract, which one of the following statements is
is a discrepancy found in a public voucher.
false.
The government's policy is for contractors to provide all
of their own general purpose equipment. However, on
a base or installation or in a contingency contracting True
environment, equipment may be accountable under the
contract as Government Property.
The government must notify the contractor when Monies are withheld or deducted for contract noncompli-
. ance.
Past performance assessments may include inputs from Legal Counsel, Contracting Oflcer, End User, Contracting
the (select all that apply) Oflcer's Representative
If the contractor delivers a non-conforming item or ser-
vice, the Contracting Oflcer
may accept the deliverable.
An example of government obligation in the performance Payment to the contractor for the supplies and services
of the contract is . delivered
The government has from receipt of an invoice
Seven days
to notify the contractor it is improper.
The Contracting Oflcer's Representative's role in inspec-
tion is to determine whether the completed supplies and
True
services conform to what the government ordered and
can be accepted.
Once the Government Representative has executed final
acceptance of any supplies or services there in no legal False
recourse for the government for non-conforming items.