Adhesive Anchor Training Exam –
Adhesive Anchor Installation and
Inspection Assessment – 2026/2027
**Q1: Which component of an adhesive anchor system directly provides the load-transfer path to the
concrete?**
A) Adhesive cartridge
B) Mixing nozzle
C) Anchor element (threaded rod or rebar)
D) Dispensing tool
**Correct Answer: C**
,**Rationale:** The anchor element (threaded rod or reinforcing bar) is the steel member that resists
the applied loads and transfers them to the concrete through the cured adhesive bond. The cartridge,
nozzle, and dispensing tool are all installation equipment, not load-bearing components .
---
**Q2: An adhesive anchor installation is considered a "system" composed of which components?**
A) Anchor only
B) Adhesive and anchor only
C) Adhesive, anchor, and tools
D) Adhesive, anchor, drilling equipment, cleaning equipment, installation equipment, MPII, and MSDS
**Correct Answer: D**
**Rationale:** The complete adhesive anchor system includes the adhesive material, the anchor
element, tools for hole preparation and installation, and the critical supporting documents:
Manufacturer's Product Installation Instructions (MPII) and Safety Data Sheets (SDS) .
---
**Q3: In an adhesive-bond failure mode, which part of the system fails first?**
A) Steel rod yielding
B) Concrete cone shear
C) Adhesive bond at the steel surface
D) Anchor head pulling out of the hole
, **Correct Answer: C**
**Rationale:** Bond failure occurs when the adhesive loses adhesion to the steel surface before any
steel or concrete failure. This underscores the importance of proper hole cleaning and surface
preparation .
---
**Q4: Which document must be reviewed to confirm that the manufacturer's installation procedure is
being followed on site?**
A) Project schedule
B) Shop drawing submittal
C) Manufacturer's Installation Instructions (MII/MPII)
D) Contractor's safety plan
**Correct Answer: C**
**Rationale:** The Manufacturer's Installation Instructions (MII) or Manufacturer's Product Installation
Instructions (MPII) provide the step-by-step procedure required for proper installation and must be
available on site. Following these instructions is essential to achieve the published anchor capacities .
---
## SECTION 2: ADHESIVE CHEMISTRY & MATERIALS
Adhesive Anchor Installation and
Inspection Assessment – 2026/2027
**Q1: Which component of an adhesive anchor system directly provides the load-transfer path to the
concrete?**
A) Adhesive cartridge
B) Mixing nozzle
C) Anchor element (threaded rod or rebar)
D) Dispensing tool
**Correct Answer: C**
,**Rationale:** The anchor element (threaded rod or reinforcing bar) is the steel member that resists
the applied loads and transfers them to the concrete through the cured adhesive bond. The cartridge,
nozzle, and dispensing tool are all installation equipment, not load-bearing components .
---
**Q2: An adhesive anchor installation is considered a "system" composed of which components?**
A) Anchor only
B) Adhesive and anchor only
C) Adhesive, anchor, and tools
D) Adhesive, anchor, drilling equipment, cleaning equipment, installation equipment, MPII, and MSDS
**Correct Answer: D**
**Rationale:** The complete adhesive anchor system includes the adhesive material, the anchor
element, tools for hole preparation and installation, and the critical supporting documents:
Manufacturer's Product Installation Instructions (MPII) and Safety Data Sheets (SDS) .
---
**Q3: In an adhesive-bond failure mode, which part of the system fails first?**
A) Steel rod yielding
B) Concrete cone shear
C) Adhesive bond at the steel surface
D) Anchor head pulling out of the hole
, **Correct Answer: C**
**Rationale:** Bond failure occurs when the adhesive loses adhesion to the steel surface before any
steel or concrete failure. This underscores the importance of proper hole cleaning and surface
preparation .
---
**Q4: Which document must be reviewed to confirm that the manufacturer's installation procedure is
being followed on site?**
A) Project schedule
B) Shop drawing submittal
C) Manufacturer's Installation Instructions (MII/MPII)
D) Contractor's safety plan
**Correct Answer: C**
**Rationale:** The Manufacturer's Installation Instructions (MII) or Manufacturer's Product Installation
Instructions (MPII) provide the step-by-step procedure required for proper installation and must be
available on site. Following these instructions is essential to achieve the published anchor capacities .
---
## SECTION 2: ADHESIVE CHEMISTRY & MATERIALS