1. A commissioning authority (CxA) is engaged during the pre-design phase of
a large healthcare facility. What is the MOST critical initial task?
A. Develop functional performance tests
B. Review contractor submittals
C. Establish the Owner’s Project Requirements (OPR)
D. Conduct site inspections
✔ Correct Answer: C. Establish the Owner’s Project Requirements (OPR)
Explanation: The OPR defines the project’s goals, benchmarks, and
performance criteria, forming the foundation of all commissioning
activities.
2. During design review, what is the PRIMARY objective of the commissioning
authority?
A. Approve design drawings
B. Verify compliance with OPR
C. Select equipment vendors
D. Conduct cost analysis
✔ Correct Answer: B. Verify compliance with OPR
Explanation: Design reviews ensure the Basis of Design aligns with the
OPR, maintaining project intent.
,3. Which document translates the OPR into technical design criteria?
A. Commissioning Plan
B. Functional Test Procedures
C. Basis of Design (BOD)
D. Systems Manual
✔ Correct Answer: C. Basis of Design (BOD)
Explanation: The BOD explains how design solutions meet the Owner’s
Project Requirements.
4. A deficiency is identified during functional testing. What is the FIRST step?
A. Notify owner
B. Document issue in log
C. Stop testing permanently
D. Redesign system
✔ Correct Answer: B. Document issue in log
Explanation: Proper documentation ensures tracking, accountability, and
resolution of issues.
5. What is the PRIMARY purpose of pre-functional checklists?
A. Verify system installation
B. Train operators
C. Test system performance
D. Conduct energy audits
✔ Correct Answer: A. Verify system installation
Explanation: Pre-functional checklists confirm systems are installed
correctly before testing.
6. Which phase includes development of the commissioning plan?
A. Construction
B. Occupancy
C. Pre-design
D. Post-occupancy
✔ Correct Answer: C. Pre-design
, Explanation: The commissioning plan is initially developed early to guide
the entire process.
7. Functional performance testing verifies:
A. Equipment cost
B. System operation under design conditions
C. Contractor qualifications
D. Code compliance only
✔ Correct Answer: B. System operation under design conditions
Explanation: Functional testing ensures systems perform as intended
under real conditions.
8. Who is responsible for maintaining the issues log?
A. Contractor
B. Owner
C. Commissioning Authority
D. Architect
✔ Correct Answer: C. Commissioning Authority
Explanation: The CxA manages and tracks all commissioning-related
issues.
9. Seasonal testing is required when:
A. Budget allows
B. Systems depend on seasonal conditions
C. Owner requests only
D. Equipment is new
✔ Correct Answer: B. Systems depend on seasonal conditions
Explanation: Certain systems require specific environmental conditions to
test performance.
10.What is the MAIN goal of commissioning?
A. Reduce construction cost
B. Ensure systems meet OPR
C. Speed project delivery