1. A special inspector is reviewing drilled shaft excavation in cohesive soil.
What is the primary concern during inspection?
A. Concrete slump
B. Sidewall stability
C. Rebar coating
D. Truck delivery time
✔ Correct Answer: B. Sidewall stability
Explanation: In cohesive soils, maintaining excavation sidewall stability is
critical to prevent collapse and ensure structural integrity of the drilled
shaft.
2. During pile driving, what is the primary purpose of a pile driving analyzer
(PDA)?
A. Measure pile length
B. Determine soil type
C. Evaluate pile capacity
D. Monitor concrete curing
✔ Correct Answer: C. Evaluate pile capacity
Explanation: A PDA assesses pile capacity and driving stresses using
dynamic measurements during installation.
3. What document governs special inspection requirements in most U.S.
jurisdictions?
A. OSHA Standards
, B. ASTM Manual
C. International Building Code (IBC)
D. ACI 301
✔ Correct Answer: C. International Building Code (IBC)
Explanation: The IBC outlines requirements for special inspections
including deep foundations.
4. A drilled shaft uses slurry for stabilization. What must be checked before
concrete placement?
A. Slurry density and viscosity
B. Air content
C. Rebar spacing
D. Cement type
✔ Correct Answer: A. Slurry density and viscosity
Explanation: Proper slurry properties ensure excavation stability and
prevent contamination of concrete.
5. What is the minimum embedment depth for piles typically based on?
A. Contractor preference
B. Soil bearing capacity
C. Weather conditions
D. Equipment availability
✔ Correct Answer: B. Soil bearing capacity
Explanation: Embedment depth is determined by soil capacity to safely
transfer loads.
6. Which test is commonly used to evaluate drilled shaft integrity?
A. Slump test
B. Crosshole Sonic Logging (CSL)
C. Proctor test
D. Sieve analysis
✔ Correct Answer: B. Crosshole Sonic Logging (CSL)
Explanation: CSL detects defects and inconsistencies in drilled shaft
concrete.
, 7. What is the function of a tremie pipe?
A. Measure depth
B. Deliver concrete underwater
C. Reinforce shaft
D. Pump slurry
✔ Correct Answer: B. Deliver concrete underwater
Explanation: Tremie pipes place concrete below slurry or water without
segregation.
8. When inspecting driven piles, what indicates refusal?
A. Excessive vibration
B. Minimal penetration per hammer blow
C. Increased noise
D. Decreased hammer speed
✔ Correct Answer: B. Minimal penetration per hammer blow
Explanation: Refusal occurs when the pile no longer advances significantly
under hammer blows.
9. What is the primary purpose of rebar cages in drilled shafts?
A. Reduce cost
B. Improve curing
C. Provide structural reinforcement
D. Increase diameter
✔ Correct Answer: C. Provide structural reinforcement
Explanation: Rebar cages resist tensile and bending forces in shafts.
10.What should be verified before concrete placement in deep foundations?
A. Worker attendance
B. Excavation cleanliness
C. Weather forecast
D. Equipment fuel levels
✔ Correct Answer: B. Excavation cleanliness
Explanation: Clean excavation ensures proper bonding and structural
integrity.