PRINCE2-Foundation Dumps - Getting Ready For The PRINCE2-Foundation Exam

Puntuación
-
Vendido
1
Páginas
8
Grado
A+
Subido en
10-06-2021
Escrito en
2020/2021

100% actual PRINCE2-Foundation dumps with updated PRINCE2-Foundation exam questions & answers. Pass the PRINCE2-Foundation exam with 99% marks. Click on download button to download the full free version of PRINCE2-Foundation dumps file.

Mostrar más Leer menos
Institución
Grado














Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Estudio
Grado

Información del documento

Subido en
10 de junio de 2021
Número de páginas
8
Escrito en
2020/2021
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

PRINCE2
PRINCE2-Foundation Exam
PRINCE2 Practitioner


Questions & Answers (Demo Version)
https://examslead.com/PRINCE2-Foundation-practice-exam-dumps/




Buy Full Product Here:

, PRINCE2
PRINCE2-FOUNDATION Exam
PRINCE2 PRINCE2 Foundation Exam

Questions & Answers
Demo

,Questions & Answers PDF Page 3




Version: 11.0

Question: 1

When considering risks, which describes an opportunity in a project?

A. An uncertain event that couldhave a negative impact on objectives
B. An uncertain event that could have a favourable impact on objectives
C. An event that has occurred resulting in a negative impact on objectives
D. An event that has occurred resulting in a favourable impact on objectives

Answer: B

Question: 2

Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down
by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred
to the Project Manager down by the Project Board.

A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true

Answer: C

Question: 3

Which may be funded from a risk budget?

A. Corrections due to off-specifications
B. Impact analysis of requests for change
C. Implementation of a fallback plan
D. Preparation of the Risk Management Strategy

Answer: C

Question: 4

,Questions & Answers PDF Page 4




What is the first task of product-based planning?

A. Produce the Initiation Stage Plan
B. Write the Project Product Description
C. Identify dependencies
D. Create the product breakdown structure

Answer: B

Question: 5

How many tasks does the product-based planning technique describe?

A. One
B. Two
C. Three
D. Four

Answer: D

Question: 6

Which is an objective of the quality review technique?

A. To identify a product's quality criteria
B. To provide assurance that the project is being conducted properly
C. To assess that a product conforms to set criteria
D. To ensure that staff are properly trained in the quality methods

Answer: C

Question: 7

Which of the following refers to the actions identified to bring a situation to a level where exposure
to a risk is acceptable?

A. Risk category
B. Risk description
C. Risk response
D. Risk status

Answer: C

Question: 8

If an informal issue is defined as a problem or concern, where should it first be recorded?

,Questions & Answers PDF Page 5




A. Issue Register
B. Risk Register
C. Daily Log
D. Exception Report

Answer: C

Question: 9

Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists exists before the
Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the
current status of a project before the Project Board authorizes a project.

A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true

Answer: C

Question: 10

Which is the purpose of the Change theme?

A. Prevent change to baselined products
B. Identify, assess and control any potential and approved changes to baselined products
C. Establish mechanisms to monitor and compare actual achievements against those planned
D. Assess and control uncertainty

Answer: B

Question: 11

Why is a Project Brief produced?

A. To act as a trigger for the Starting up a Project process
B. To record the strategies andmanagement controls to be used by a project
C. To provide a full and firm foundation for the initiation of a project
D. To be used by the Project Board as a basis for reviewing the progress of a project

Answer: C

Question: 12

,Questions & Answers PDF Page 6




Identify the missing words in the following sentence. An objective of the Closing a Project process is
to ensure that provision has been made to address [?] through follow-on action recommendations.

A. the measurement of benefits NOT yet realized
B. the handover of products
C. open issues and risks
D. the release of resources

Answer: C

Question: 13

In what process is the authorization to deliver the project's products given?

A. Starting up a Project
B. Initiating a Project
C. Managing a Stage Boundary
D. Directing a Project

Answer: D

Question: 14

Which of the following is NOT part of quality planning?

A. Define quality responsibilities
B. Gain acceptance of the project product
C. Agree acceptance criteria
D. Set quality tolerances

Answer: B

Question: 15

Which should be provided by a project mandate?

A. Terms of reference
B. Detailed Business Case
C. Stage tolerances
D. Initiation Stage Plan

Answer: A

Question: 16

, Questions & Answers PDF Page 7




Which is an objective of the Starting up a Project process?

A. Identify who will be responsible for creating the Project Plan
B. Agree how the project will be monitored and controlled after initiation
C. Authorize the Project Manager to proceed with the initiation stage
D. Agree how issues and changes will be identified, assessed and controlled

Answer: A

Question: 17

Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to
reflect the needs of the different levels of management involved in a project,

A. Management strategies
B. Plan
C. Stakeholder interests
D. Time-driven controls

Answer: B

Question: 18

If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a
decision?

A. Senior User
B. Executive
C. Corporate/programme management
D. Senior Supplier

Answer: C
Gratis
Accede al documento completo:
Descarga

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor
Seller avatar
meganalsop

Conoce al vendedor

Seller avatar
meganalsop Exam Dumps
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
2
Miembro desde
4 año
Número de seguidores
2
Documentos
12
Última venta
4 año hace
Just Actual Dumps

Learn All Certifications Exam Topics & Objectives

0.0

0 reseñas

5
0
4
0
3
0
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes