1. What is the primary purpose of contract administration?
A. To negotiate only contract prices
B. To ensure contract terms are properly executed and
enforced
C. To draft new legislation
D. To eliminate procurement processes
Rationale: Contract administration focuses on monitoring and
enforcing contract performance after award.
Correct Answer: B
2. Which document formally authorizes work to begin under a
contract?
A. Invoice
B. Purchase requisition
C. Notice to Proceed (NTP)
D. Bid proposal
,Rationale: The Notice to Proceed officially authorizes the
contractor to start work.
Correct Answer: C
3. What is a key responsibility of a contract administrator?
A. Performing criminal investigations
B. Ensuring compliance with contract terms
C. Approving criminal sentencing
D. Writing legislation
Rationale: Contract administrators monitor compliance with
agreed terms.
Correct Answer: B
4. What does “scope of work” define in a contract?
A. Payment schedule
B. Legal penalties
C. Detailed description of services or deliverables
D. Employee salaries
Rationale: Scope of work outlines tasks, deliverables, and
expectations.
Correct Answer: C
5. Which phase comes first in the contract lifecycle?
,A. Contract closeout
B. Contract performance
C. Procurement planning
D. Contract termination
Rationale: Procurement planning initiates the contract lifecycle.
Correct Answer: C
6. What is a contract modification?
A. Cancellation of a contract
B. A change to contract terms after execution
C. A bid submission
D. A legal lawsuit
Rationale: Modifications alter terms, scope, or pricing after
signing.
Correct Answer: B
7. What is the purpose of performance monitoring?
A. To increase taxes
B. To ensure contractors meet obligations
C. To terminate employees
D. To write policies
Rationale: Monitoring ensures compliance with contract
requirements.
Correct Answer: B
, 8. What is a deliverable?
A. A payment method
B. A measurable output required by the contract
C. A legal penalty
D. A procurement form
Rationale: Deliverables are tangible or measurable outputs.
Correct Answer: B
9. What does “breach of contract” mean?
A. Successful completion of contract
B. Failure to fulfill contractual obligations
C. Renewal of contract
D. Signing of contract
Rationale: A breach occurs when obligations are not met.
Correct Answer: B
10. What is contract closeout?
A. Beginning of negotiations
B. Final settlement and completion of contract obligations
C. Awarding of contract
D. Drafting of scope