1. A construction manager is reviewing contract documents and identifies
discrepancies between drawings and specifications. What is the MOST
appropriate initial action? ✓
A. Ignore the discrepancy
B. Issue a request for information (RFI)
C. Revise the drawings independently
D. Halt all construction work
Answer: B. Issue a request for information (RFI)
Explanation: The correct answer is (Issue a request for information (RFI))
because an RFI formally clarifies inconsistencies between contract
documents before proceeding, ensuring accuracy and avoiding liability.
2. Which project delivery method places the MOST risk on the contractor? ✓
A. Cost-plus contract
B. Design-bid-build
C. Lump sum (fixed price)
D. Construction management at risk
Answer: C. Lump sum (fixed price)
Explanation: The correct answer is (Lump sum (fixed price)) because the
contractor assumes full responsibility for cost overruns under a fixed
contract amount.
,3. What is the primary purpose of a project baseline schedule? ✓
A. Track labor productivity
B. Establish initial project timeline for comparison
C. Monitor safety incidents
D. Approve subcontractor payments
Answer: B. Establish initial project timeline for comparison
Explanation: The correct answer is (Establish initial project timeline for
comparison) because it serves as the benchmark against which actual
progress is measured.
4. In earned value management, what does CPI stand for? ✓
A. Cost Performance Index
B. Construction Progress Indicator
C. Cost Planning Initiative
D. Critical Path Index
Answer: A. Cost Performance Index
Explanation: The correct answer is (Cost Performance Index) because CPI
measures cost efficiency by comparing earned value to actual cost.
5. A project is behind schedule but under budget. Which action is MOST
appropriate? ✓
A. Reduce workforce
B. Increase project scope
C. Accelerate schedule using additional resources
D. Delay project completion
Answer: C. Accelerate schedule using additional resources
Explanation: The correct answer is (Accelerate schedule using additional
resources) because being under budget allows allocation of resources to
recover schedule delays.
6. What is the primary function of a change order? ✓
A. Approve initial design
B. Modify contract scope, cost, or time
C. Close out project
, D. Approve subcontractors
Answer: B. Modify contract scope, cost, or time
Explanation: The correct answer is (Modify contract scope, cost, or time)
because change orders formalize adjustments to the original agreement.
7. Which document defines project scope in detail? ✓
A. Bid form
B. Scope statement
C. Invoice
D. Safety manual
Answer: B. Scope statement
Explanation: The correct answer is (Scope statement) because it clearly
outlines project deliverables and boundaries.
8. What is the critical path in scheduling? ✓
A. Shortest path in project
B. Longest sequence of activities determining project duration
C. Least expensive tasks
D. Optional activities
Answer: B. Longest sequence of activities determining project duration
Explanation: The correct answer is (Longest sequence of activities
determining project duration) because delays on this path directly affect
completion time.
9. Which contract type is MOST flexible for scope changes? ✓
A. Lump sum
B. Unit price
C. Cost-plus
D. Fixed price incentive
Answer: C. Cost-plus
Explanation: The correct answer is (Cost-plus) because it allows adjustments
as actual costs evolve.
, 10.A safety audit reveals repeated violations. What should the construction
manager do FIRST? ✓
A. Terminate workers
B. Report to authorities immediately
C. Conduct corrective training
D. Ignore minor violations
Answer: C. Conduct corrective training
Explanation: The correct answer is (Conduct corrective training) because
addressing root causes through education improves compliance.
11.What is the main goal of value engineering? ✓
A. Increase project duration
B. Reduce quality
C. Optimize cost and function
D. Eliminate stakeholders
Answer: C. Optimize cost and function
Explanation: The correct answer is (Optimize cost and function) because
value engineering improves efficiency without compromising performance.
12.Which stakeholder has ultimate authority in project decisions? ✓
A. Contractor
B. Owner
C. Subcontractor
D. Supplier
Answer: B. Owner
Explanation: The correct answer is (Owner) because they fund the project
and have final decision-making authority.
13.What is float in scheduling? ✓
A. Budget reserve
B. Extra time available for an activity
C. Labor surplus
D. Material waste
Answer: B. Extra time available for an activity