1. A project manager is reviewing the project scope statement. Which
document provides the most detailed description of project deliverables
and boundaries?
A. Work Breakdown Structure
B. Project Charter
C. Scope Management Plan
D. Schedule Baseline
✔ Correct Answer: A (Work Breakdown Structure)
The Work Breakdown Structure (WBS) breaks down deliverables into
smaller components, providing the most detailed scope definition.
2. During site preparation, a contractor discovers unforeseen soil conditions.
What is the first action the associate constructor should take?
A. Proceed with alternative foundation
B. Notify owner and document condition
C. Stop all work permanently
D. Redesign without approval
✔ Correct Answer: B (Notify owner and document condition)
Proper documentation and communication ensure contractual protection
and allow for formal change management.
,3. Which contract type places the greatest risk on the contractor?
A. Cost-plus contract
B. Time and materials
C. Lump sum contract
D. Unit price contract
✔ Correct Answer: C (Lump sum contract)
In a lump sum contract, the contractor bears the risk of cost overruns
since the price is fixed.
4. What is the primary purpose of a project schedule?
A. Estimate labor costs
B. Track material deliveries
C. Define project timeline and sequence
D. Control quality
✔ Correct Answer: C (Define project timeline and sequence)
A schedule outlines activities, durations, and sequencing to guide project
execution.
5. Which document formally authorizes a construction project?
A. Bid proposal
B. Project charter
C. Contract agreement
D. Notice to proceed
✔ Correct Answer: D (Notice to proceed)
The Notice to Proceed officially authorizes the contractor to begin work.
6. A critical path is best described as:
A. The shortest project path
B. The path with most resources
C. The longest duration path
D. The least expensive path
✔ Correct Answer: C (The longest duration path)
The critical path determines the minimum project duration and includes
activities with zero float.
,7. Float in scheduling refers to:
A. Cost overrun allowance
B. Extra materials
C. Time an activity can be delayed
D. Labor inefficiency
✔ Correct Answer: C (Time an activity can be delayed)
Float indicates flexibility in scheduling without impacting the project
completion date.
8. Which safety standard governs construction sites in the U.S.?
A. ANSI
B. OSHA
C. EPA
D. ISO
✔ Correct Answer: B (OSHA)
OSHA establishes and enforces workplace safety regulations for
construction.
9. What is the purpose of a submittal?
A. Request payment
B. Approve materials and methods
C. Report accidents
D. Track labor
✔ Correct Answer: B (Approve materials and methods)
Submittals ensure that materials and equipment meet design
specifications before installation.
10.A change order is used to:
A. Reject materials
B. Modify contract scope or cost
C. Delay schedule
D. Terminate contract
✔ Correct Answer: B (Modify contract scope or cost)
Change orders formally adjust scope, cost, or schedule under the contract.
, 11.Which method estimates costs based on historical data?
A. Parametric estimating
B. Analogous estimating
C. Bottom-up estimating
D. Three-point estimating
✔ Correct Answer: B (Analogous estimating)
Analogous estimating uses past project data to predict current costs.
12.What is the main function of quality control?
A. Plan quality
B. Ensure compliance with standards
C. Hire labor
D. Manage contracts
✔ Correct Answer: B (Ensure compliance with standards)
Quality control focuses on inspection and testing to meet specifications.
13.Which document outlines how risks are managed?
A. Risk register
B. Risk management plan
C. Safety plan
D. Scope statement
✔ Correct Answer: B (Risk management plan)
This plan defines processes for identifying, analyzing, and responding to
risks.
14.A unit price contract is most suitable when:
A. Scope is fixed
B. Quantities are uncertain
C. Costs are fixed
D. Time is critical
✔ Correct Answer: B (Quantities are uncertain)
Unit price contracts allow flexibility when quantities cannot be accurately
determined.