1. A plans examiner reviewing a commercial building application
identifies that the proposed occupancy is classified as Group A-2.
Which code section is MOST relevant in determining allowable
construction type and fire protection requirements?
A. Chapter 3 of the International Building Code
B. Chapter 5 of the International Building Code
C. Chapter 9 of the International Building Code
D. Chapter 10 of the International Building Code
Answer: B
A Group A-2 occupancy relates directly to occupancy classification
and allowable building height and area, which are governed
primarily by Chapter 5 of the International Building Code, making it
the correct reference for determining construction type and
limitations.
2. A submitted plan shows a building exceeding allowable height for its
construction type. What is the MOST appropriate initial action for a
plans examiner?
, A. Approve with conditions
B. Deny permit immediately
C. Request code modification approval from the state
D. Issue correction comments requesting compliance adjustments
Answer: D
A plans examiner must first provide correction comments allowing
the applicant to revise plans for compliance before denial or
escalation, ensuring due process and opportunity for correction.
3. Which document provides the PRIMARY basis for determining
structural load requirements in most ICC plan reviews?
A. International Mechanical Code
B. International Building Code
C. International Plumbing Code
D. International Fire Code
Answer: B
Structural load requirements, including live, dead, wind, and seismic
loads, are governed by the International Building Code, making it the
primary reference for structural review.
4. A plan reviewer notices conflicting information between architectural
and structural drawings. What should the examiner do FIRST?
A. Choose the more detailed drawing
B. Reject the application immediately
C. Issue a request for clarification or coordination
D. Approve based on architect’s seal
Answer: C
When discrepancies exist, the examiner must request clarification or
coordination from the design professionals to ensure accurate and
consistent construction documents.
,5. What is the primary purpose of a code analysis section in submitted
plans?
A. To summarize contractor pricing
B. To identify applicable codes and design criteria
C. To replace permit review
D. To list inspection schedules
Answer: B
The code analysis section identifies governing codes, occupancy
classification, and design criteria, helping reviewers verify
compliance efficiently.
6. Which occupancy classification applies to a building primarily used for
residential sleeping units?
A. Group B
B. Group S
C. Group R
D. Group F
Answer: C
Group R occupancies cover residential buildings where people live or
sleep, making it the correct classification for dwelling units.
7. A building includes mixed occupancies separated by fire barriers. What
determines whether they can be considered separated occupancies?
A. HVAC zoning
B. Fire-resistance-rated separation
C. Plumbing layout
D. Parking ratio
Answer: B
Separated occupancies are defined by fire-resistance-rated barriers
that prevent fire spread between distinct occupancy types.
, 8. Which code governs accessibility requirements in most ICC plan
reviews?
A. International Existing Building Code
B. ICC A117.1 Accessibility Standard
C. International Zoning Code
D. NFPA 13
Answer: B
ICC A117.1 provides technical accessibility standards commonly
referenced in building plan reviews for compliance with accessibility
requirements.
9. A proposed exit door swings into a required exit corridor and reduces
clear width. What is the correct code concern?
A. Plumbing clearance
B. Egress obstruction
C. Structural load issue
D. Energy compliance issue
Answer: B
Any reduction of required egress width or obstruction of exit paths is
an egress violation under life safety provisions.
10. Which factor is MOST critical when evaluating allowable building
area increases?
A. Roof color
B. Fire sprinkler system installation
C. Interior paint type
D. Landscaping design
Answer: B
Fire sprinkler systems can significantly increase allowable building
area under code provisions, making them a critical factor in plan
review.