The sum of the activity times on the critical path determines
_____________________. - correct-answer -minimum time to complete the
project
In making a backward pass through a network, activity L has an activity time of 4
and immediately precedes activities M, P, and T. The late start times for activities
M, P, and T are 22, 17, and 27, respectively. The late finish times for activities M,
P, and T are 29, 27, and 33, respectively. What is the late start time for activity L?
- correct-answer -13
, 2|Page
In making a backward pass through a network, activity L has an activity time of 4
and immediately precedes activities M, P, and T. The late start times for activities
M, P, and T are 22, 17, and 27, respectively. The late finish times for activities M,
P, and T are 29, 27, and 33, respectively. What is the late finish time for activity L?
- correct-answer -17
Given this information about an activity: ES = 10, EF = 20, LS = 29, and LF = 39. The
amount of slack associated with the activity is ____________________. - correct-
answer -19
You may be able to speed up completion of a project by
_______________________. - correct-answer -making additional resources
available
Which of the following is not included in the approach for crashing projects? -
correct-answer -Determine which activity requires the most time.
MKTG 372 FINAL REGO
EXAM|ACTUAL QUESTIONS WITH
ANSWERS
The sum of the activity times on the critical path determines
_____________________. - correct-answer -minimum time to complete the
project
In making a backward pass through a network, activity L has an activity time of 4
and immediately precedes activities M, P, and T. The late start times for activities
M, P, and T are 22, 17, and 27, respectively. The late finish times for activities M,
P, and T are 29, 27, and 33, respectively. What is the late start time for activity L?
- correct-answer -13
, 2|Page
In making a backward pass through a network, activity L has an activity time of 4
and immediately precedes activities M, P, and T. The late start times for activities
M, P, and T are 22, 17, and 27, respectively. The late finish times for activities M,
P, and T are 29, 27, and 33, respectively. What is the late finish time for activity L?
- correct-answer -17
Given this information about an activity: ES = 10, EF = 20, LS = 29, and LF = 39. The
amount of slack associated with the activity is ____________________. - correct-
answer -19
You may be able to speed up completion of a project by
_______________________. - correct-answer -making additional resources
available
Which of the following is not included in the approach for crashing projects? -
correct-answer -Determine which activity requires the most time.