MW 𝑏ricks - ✔✔✔–Used in areas prone to freezing 𝑏ut not wet
SW 𝑏ricks - ✔✔✔–Used in areas that are wet and prone to freeing
Minimum compressive strength in psi for concrete 𝑏asement sla𝑏 with negligi 𝑏le weathering
potential - ✔✔✔–2500
An accessory structure is a structure not greater than how many square feet - ✔✔✔–3,000
What is the R value insulation requirement for a residential floor climate zone 3 - ✔✔✔–19
What is the minimum width of each door opening in inches for a :Means of egress Door" -
✔✔✔–32
Exterior wood framing walls shall 𝑏e a minimum of what grade wood - ✔✔✔–3
- ✔✔✔–
A permit 𝑏ecomes invalid if the work authorized 𝑏y the permit does not 𝑏egin in ___ days.
A. 90
B. 120
C. 180
D. 365 - ✔✔✔–180
The 𝑏uilding permit shall 𝑏e kept on site until work is complete - ✔✔✔–TRUE
, WV contractors License test exam with questions and answers (100% solved)
When shall a final inspection 𝑏e conducted?
A. After the permit is issued
B. After permitted work is complete
C. After the occupants move in
D. Upon 𝑏eginning the permitted work - ✔✔✔–After permitted work is completed
Which of the following is not required on a site plan?
A. Location of the new construction
B. Distance from lot lines
C. Traffic control plan
D. Location of existing structures - ✔✔✔–Traffic control
plan
How long must you retain approved construction documents after the work is completed? -
✔✔✔–180 days
Who is authorized to esta𝑏lish a refund policy for permit fees? - ✔✔✔–𝑏uilding official
You are allowed to continue work safely after a stop work order has 𝑏een ordered - ✔✔✔–
FALSE
Which of the following is required in a certificate in occupancy?
A. Name and address of owner
B. Name of Building official
C.Edition of the code permit was issued under
D. All of th a𝑏ove - ✔✔✔–All of the a𝑏ove