This document focuses on the advanced topics required for the Virginia Contractors Class A licensing exam, including complex project management, financial management, and advanced business law. It provides structured study notes along with practice questions and answers to support thorough exam preparation. The content is tailored to match the official exam requirements and help candidates succeed on their first attempt.

Mostrar más Leer menos
Institución
A Contractors Advanced
Grado
A Contractors Advanced

Vista previa del contenido

(VA Contractors VA Advanced (Class A),: 2026 Test Preparation)
VA Contractors: VA Advanced (Class A)
Study online at https://quizlet.com/_bys72d

1. A lump sum contract on a project has a total contract More than $50,000
price of $160,000. Retainage has been held back at
10%. The contractor has received progress payments
for 75% of the project. The contractor submits a re-
quest for final payment for the new completed project.
The final payment amount should be for...

2. What is the total value of current assets for an accrual Between $12,000 and
basis company that has the following? Checking ac- $16,000
count cash balance is $4,800; materials inventory for
work-in-progress is $4,200; a pick-up truck that cost
$12,460- paid for with $2,460 in cash and a note for
$10,000- and is used 100% in the business; accounts
receivable is $5,700; suppliers' accounts payable is
$6,300; other accounts payable is $2,200; and quarter-
ly income tax payment due is $1,180...

3. What is the total project overhead for a project that Less than $12,000
lasts 3 months and has the following costs? Labor is
$4,000; materials are $9,500; equipment rentals are
$1,200; superintendent's annual salary is $36,000; of-
fice rent is $800 per month; and office utilities are
$375 per month.

4. For 1 month a company bills out $38,000 in completed Loss of $1,000
work, and receives $22,000 in payments plus $8,000
from the previous month's billings. They pay their total
bill of $26,000 to supply houses for this month's pur-
chases, and another $5,000 to supply houses for last
month's purchases. Using a cash accounting method
and NOT considering any other revenue or expenses,
what is the company's net income for the month?
1/6
Page 1 3/30/2026, 4:48:56 PM

, (VA Contractors VA Advanced (Class A),: 2026 Test Preparation)
VA Contractors: VA Advanced (Class A)
Study online at https://quizlet.com/_bys72d

5. The owner requests for change which will cost the con- A decrease of $3,780
tractor $15,000 in labor and materials and $2,250 in
overhead costs. With the change, the contractor would
be relieved of $18,000 in labor and materials costs, and
$2,400 in overhead costs from the original contract.
The original bid included profit of 20% of all costs. The
contractor wants to make a profit of 20% of all costs
on the changes. The adjusted contract price for the
change order should be...

6. Which of the following would typically be covered by a Damage to adjoining
contractor's comprehensive general liability insurance property from a crane ac-
policy? cident

7. What is the total gross compensation and employment The carpenter is an em-
status for a carpenter, given the following information? ployee and is owed
A contractor hires a carpenter to do the finish work for $10,560 for the project
a 10-home project. The carpenter is to be paid $16 per
hour. The contractor provides all materials and equip-
ment, such as a table saw. The carpenter provides all
of his own hand tools. The contractor and the carpen-
ter agree that all of the homes are to be completed
within 60 8-hour working days, without overtime. The
contractor provides the carpenter with a schedule of
the order in which homes are to be worked on. The
contractor provides a helper to assist the carpenter.
The contractor sets the work schedule each day. The
carpenter spends 600 hours to complete this project,
including 120 hours of overtime.

8. What is the name of the process when a facilitator Partnering
meets with the major participants in a project, prior
2/6
Page 2 3/30/2026, 4:48:56 PM

Escuela, estudio y materia

Institución
A Contractors Advanced
Grado
A Contractors Advanced

Información del documento

Subido en
31 de marzo de 2026
Número de páginas
6
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

$14.99
Accede al documento completo:

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
doingqwerty Harvard University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
447
Miembro desde
9 meses
Número de seguidores
0
Documentos
227
Última venta
1 día hace

4.5

4 reseñas

5
2
4
2
3
0
2
0
1
0

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes