E_ACTAI_2601
SAP Certified - Project Manager - SAP Activate for Agile
Implementation Management Latest Version: 7.1
Subjects
1. SAP Activate Overview
2. Workstreams Overview
3. Agile Project Delivery
4. New Implementation SAP S/4HANA Cloud
5. Agile Project Planning
6. SAP Activate Elements
7. SAP Cloud ALM
Topic: 1
SAP Activate Overview
, Question: 1
What does a cutover involve? Note: There are 2 correct answers to this question.
A. Completing solution end-user documentation
B. Switching productive operations to new system
C. Presenting completed functionality to key users
D. Aligning business and technical cutover plans
Answer: B, D
SAP Activate Overview
Question: 2
What is the basis for approving work results (signing Act of Acceptance) on Project Phase level?
A. Steering committee meeting decision
B. Definition of Done for User Story
C. Agreed and met Acceptance Criteria within quality gate
D. Definition of Done for Sprint
Answer: C
SAP Activate Overview
Question: 3
When do you perform Quality Gate (Q-Gate) during a project? Note: There are 2 correct answers to this
question.
A. At the end of Realize phase
B. At the end of Prepare phase
C. At the end of Discover phase
D. At the end of Run phase
Answer: A, B
SAP Activate Overview
Question: 4
What solution operations framework can customers use to create a joint business and IT organization?
A. Customer Center of Expertise
B. SAP Roadmap Explorer
, C. Solution Standardization Board
D. Transformation Management Office
Answer: B
SAP Activate Overview
Question: 5
What activity do you perform in the Deploy phase?
A. Final assessment of data quality
B. Perform productive cutover
C. Complete integration testing
D. Implement operations processes
Answer: B
SAP Activate Overview
Question: 6
What are some of the key characteristics of the implementation approach in the SAP Activate
methodology? Note: There are 2 correct answers to this question.
A. Fixed scope
B. Cloud ready
C. Scaled agile framework built in
D. Based on ready-to-use content
Answer: B, D
Topic: 2
Workstreams Overview
Question: 7
In SAP Activate, what tool is used in the agile delivery approach during the Realize phase to make
forecasts based on actual data?
A. Scrum board B.
Product backlog
C. Burndown chart
D. Release plan
Answer: C