Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Examen

WGU - C722 PROJECT MANAGEMENT OA ACTUAL EXAM WITH VERIFIED QUESTIONS AND CORRECT ANSWERS GRADED A+ || 100% GUARANTEED PASS LATEST UPDATED VERSION

Puntuación
-
Vendido
-
Páginas
42
Grado
A+
Subido en
14-03-2026
Escrito en
2025/2026

WGU - C722 PROJECT MANAGEMENT OA ACTUAL EXAM WITH VERIFIED QUESTIONS AND CORRECT ANSWERS GRADED A+ || 100% GUARANTEED PASS LATEST UPDATED VERSION PCIC Equation - Answer ️PCIC = AC / EAC Actual Cost / Estimated Cost at Completion ETC - Answer ️Estimate to Completion How much money will need to complete the project ETC = (BAC - EV)/CPI (Budget at Completion - Earned Value) / Cost Performance Index CPI = EV/AC EAC - Answer ️Estimate at Completion Forecast of how much more the project is expected to cost to complete EAC = AC + ETC Actual Cost = Estimate to Completion ETC = (BAC - EV)/CPI [Cost performance index] CPI = EV/AC EVA - Answer ️Earned Value Assessment EVA Process Step 1 - Answer ️Collect measures from project records: 1. AC - Actual Cost 2. EV - Earned Value 3. PV - Planned Value 4. BAC - Budget at Completion EVA Process Step 2 - Answer ️Calculate Variances: 1. CV - Cost Variance 2. SV - Schedule Variance 3. PCIB - Percent complete index budget EVA Process Step 3 - Answer ️Calculate Performance Factors 1. CPI - Cost Performance Index 2. SPI - Schedule Performance Index EVA Process Step 4 - Answer ️Calculate Estimates or Identifying Performance Factors 1. ETC - Estimate to completion 2. EAC - Estimate at completion 3. TCPI - To complete performance Index 4. PCIB - Percent complete index budget or PCIC - (Percent complete index - cost) operations - Answer ️are the ongoing, daily activities of an organization that produces revenue and expense. project - Answer ️is an activity or group of activities to generate a new, unique product, service, or results to support that program. However, it is possible that not all projects will be part of a larger program. There could, for example, be a project to develop a new battery that is more adaptable to more extreme temperature conditions. The product of this project could be applicable to all existing automobiles and not strictly a single program. portfolio - Answer ️is a group of related programs that support a long-term company goal or objective. The projects in a portfolio may individually address separate initiatives within the organization but collectively move the organization toward meeting a long-term goal or objective. business strategy - Answer ️consists of the activities, methods, tactics, etc. that will be employed to meet the business's goals. program - Answer ️is a group of related projects. project management - Answer ️the application of knowledge, skills, tools and techniques to project activities. Phases of the Project Life Cycle - Answer ️Defining (intializing), Planning, executing and closing Defining - Answer ️Determining the project's sponsor and the project's manager Creating a project charter. The charter is a document that, like a contract, is agreed upon by the sponsor and key stakeholders. It defines the project and authorizes the resources, roles, responsibilities, authorities, and scope for the project. Planning - Answer ️Technology Business process Staffing Training Testing Communications Budget constraints Integration of the project with operations and other projects Executing - Answer ️Unexpected changes that may present themselves in the competitive environment New organizational priorities Loss of key project resources Previously unidentified risks surfacing that puts the project plans in jeopardy Closing - Answer ️The closing phase of the project occurs when the project is completed to the customers' satisfaction. triple constraint - Answer ️cost (budget), schedule (time), and scope (deliverables). Project Manager (PM) - Answer ️is responsible and accountable for managing the project to maximize its success "working" project manager - Answer ️a functional manager "dedicated" project manager - Answer ️role in life is to be a project manager regardless of the operational needs of the business. Functional (Departmentalized) - Answer ️is the oldest and most basic form of organization. It is the type of organization most often represented in corporation shareholder reports Projectized - Answer ️subject matter experts (SMEs) from different functional areas are assigned to directly report to the project manager (PM) for a specific project. Matrix - Answer ️has less clearly defined lines of reporting. Business scenario - Answer ️represents an important business need or issue and provides an opportunity for others to create an appropriate, valuable solution Project objectives - Answer ️the following are typically determined by the project sponsor and are intended to be very specific in order to appropriately communicate project expectations. SMART Active listening - Answer ️the following is important to understanding what others are saying both verbally and nonverbally and for effective project management Stakeholder engagement - Answer ️the following is the process of communicating and interacting with stakeholders in a way that keeps them interested and focused on their involvement in the project Team status reports - Answer ️reports are often updated in an online collaboration tool and published weekly Work breakdown schedules - Answer ️ensures that everyone understands what has to be delivered and who is responsible to do what when 8 and 80 Rule - Answer ️a project manager should avoid controlling tasks that take less than eight hours and should not let more than two weeks go by without checking in project management maturity model (OPM3) five levels - Answer ️1. "Ad Hoc" No formal standards, processes, methods, procedures, or staff to constitute a project management discipline. Standard technologies and reporting are sporadic 2."Planned" Project management standards, processes, methods, procedures, and staff exist in the organization, but are not considered to be an organizational standard. Basic documentation exists, inconsistent management support rarely/occasionally applied. 3."Managed" All project management standards, processes, methods, procedures, and staff are in place as organizational standards. Formal documentation exists, consistent management support, execution irregularly/inconsistently applied. 4."Integrated" More refined project management standards, processes, methods, procedures, and staff are in place. More refined documentation, consistent management support, consistent execution, and efficiency exist across all projects. Metrics are in place to collect performance data across all projects. 5."Sustained" Lessons learned and best practices are applied to continuously improve existing standards, processes, methods, procedures, and staff. Metrics are collected and applied at the project, portfolio, and organizational levels. The organization is in a position to evaluate future decisions based on past performance and maximize its competitive advantage in the industry. Weekly internal status meeting - Answer ️kind of meeting each leader speak to the status of their work and project risks, and explain the status of any mitigation activities. Advantages of Functional (Departmentalized) - Answer ️Lines of authority are clear. Departmental work is easily prioritized by identified departmental authority. There is flexibility in the use of staff. Subject matter experts (SME) available to work on multiple projects. Knowledge and experience readily shared between functional specialists. Technical continuity exists within the organization. Professional growth and career paths for the staff are clearly defined. disadvantages of Functional (Departmentalized) - Answer ️Utilizing resources across functions can be difficult. Requests for assistance from other departments not easily prioritized. It is inefficient for projects requiring collaboration/cooperation between departments. Project customer is not the only focus. Organization does not focus on solving project business issues. Project does not have a single individual responsible for all aspects of the project. Response to customer needs is slow and difficult. Project issues are not all given the same level of attention. Project is not managed holistically. Advantages of Projectized - Answer ️Clear lines of authority, the project manager has full authority. Once SMEs are assigned, there is less need to negotiate availability of resources. Project is managed holistically. Response to customer and stakeholder issues is faster and clearer. Skilled project team can support several successive projects of the same type. Timely decision making on project issues. Organizational structure is simple, flexible, and easy to understand.

Mostrar más Leer menos
Institución
WGU - C722
Grado
WGU - C722

Vista previa del contenido

WGU - C722 PROJECT MANAGEMENT OA
ACTUAL EXAM WITH VERIFIED
QUESTIONS AND CORRECT ANSWERS
GRADED A+ || 100% GUARANTEED PASS
LATEST UPDATED VERSION

PCIC Equation - Answer PCIC = AC / EAC
Actual Cost / Estimated Cost at Completion


ETC - Answer Estimate to Completion
How much money will need to complete the project


ETC = (BAC - EV)/CPI


(Budget at Completion - Earned Value) /
Cost Performance Index


CPI = EV/AC


EAC - Answer Estimate at Completion
Forecast of how much more the project is expected to cost to complete


EAC = AC + ETC

,Actual Cost = Estimate to Completion


ETC = (BAC - EV)/CPI [Cost performance index]
CPI = EV/AC


EVA - Answer Earned Value Assessment


EVA Process Step 1 - Answer Collect measures from project records:
1. AC - Actual Cost
2. EV - Earned Value
3. PV - Planned Value
4. BAC - Budget at Completion


EVA Process Step 2 - Answer Calculate Variances:
1. CV - Cost Variance
2. SV - Schedule Variance
3. PCIB - Percent complete index budget


EVA Process Step 3 - Answer Calculate Performance Factors
1. CPI - Cost Performance Index
2. SPI - Schedule Performance Index


EVA Process Step 4 - Answer Calculate Estimates or Identifying Performance
Factors
1. ETC - Estimate to completion

,2. EAC - Estimate at completion
3. TCPI - To complete performance Index
4. PCIB - Percent complete index budget or
PCIC - (Percent complete index - cost)


operations - Answer are the ongoing, daily activities of an organization that
produces revenue and expense.


project - Answer is an activity or group of activities to generate a new, unique
product, service, or results to support that program. However, it is possible that not
all projects will be part of a larger program. There could, for example, be a project
to develop a new battery that is more adaptable to more extreme temperature
conditions. The product of this project could be applicable to all existing
automobiles and not strictly a single program.


portfolio - Answer is a group of related programs that support a long-term
company goal or objective. The projects in a portfolio may individually address
separate initiatives within the organization but collectively move the organization
toward meeting a long-term goal or objective.


business strategy - Answer consists of the activities, methods, tactics, etc. that
will be employed to meet the business's goals.


program - Answer is a group of related projects.


project management - Answer the application of knowledge, skills, tools and
techniques to project activities.

, Phases of the Project Life Cycle - Answer Defining (intializing), Planning,
executing and closing


Defining - Answer Determining the project's sponsor and the project's manager
Creating a project charter. The charter is a document that, like a contract, is agreed
upon by the sponsor and key stakeholders. It defines the project and authorizes the
resources, roles, responsibilities, authorities, and scope for the project.


Planning - Answer Technology
Business process
Staffing
Training
Testing
Communications
Budget constraints
Integration of the project with operations and other projects


Executing - Answer Unexpected changes that may present themselves in the
competitive environment
New organizational priorities
Loss of key project resources
Previously unidentified risks surfacing that puts the project plans in jeopardy


Closing - Answer The closing phase of the project occurs when the project is
completed to the customers' satisfaction.

Escuela, estudio y materia

Institución
WGU - C722
Grado
WGU - C722

Información del documento

Subido en
14 de marzo de 2026
Número de páginas
42
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

$16.19
Accede al documento completo:

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Conoce al vendedor
Seller avatar
TutorEric

Conoce al vendedor

Seller avatar
TutorEric Teachme2-tutor
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1
Miembro desde
1 año
Número de seguidores
0
Documentos
107
Última venta
10 meses hace
ACADEMIC HUB

As a professional tutor, I provide high-quality academic support in Nursing, Psychology, Business, Sciences, and Mathematics. We provide scholarly assignments, research support, revision materials, and exam preparation, helping students achieve excellent grades through accurate, timely, and standards-based academic assistance.

0.0

0 reseñas

5
0
4
0
3
0
2
0
1
0

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes