1. A product owner wants the team to deliver the highest business value early
in the project. Which Agile practice best supports this goal?
A. Developing a full detailed plan at project start
B. Prioritizing the product backlog based on value
C. Assigning tasks based on team member seniority
D. Freezing requirements after sprint one
Correct Answer: B. Prioritizing the product backlog based on value
Agile emphasizes delivering the highest business value first. Prioritizing backlog
items ensures the most valuable features are developed early.
2. During a daily stand-up meeting, what is the primary purpose of team
members sharing updates?
A. Reporting progress to the project sponsor
B. Updating management reports
C. Synchronizing work and identifying impediments
D. Assigning new work to team members
,Correct Answer: C. Synchronizing work and identifying impediments
Daily stand-ups are meant to align the team’s work and quickly surface obstacles
that may block progress.
3. A team notices defects frequently occur late in the sprint. Which Agile
practice helps detect issues earlier?
A. Big design up front
B. Continuous integration
C. Phase-gate reviews
D. Monthly stakeholder meetings
Correct Answer: B. Continuous integration
Continuous integration frequently merges and tests code, allowing issues to be
detected early in development.
4. What is the main responsibility of a Scrum Master?
A. Approving the project budget
B. Managing stakeholder expectations
C. Removing impediments and supporting the team
D. Assigning tasks to developers
Correct Answer: C. Removing impediments and supporting the team
The Scrum Master facilitates Agile practices and removes obstacles so the team
can work efficiently.
5. In Agile projects, requirements are typically documented in the form of:
A. Work breakdown structures
B. Business cases
C. User stories
D. Project charters
Correct Answer: C. User stories
, User stories capture requirements from the user’s perspective and help teams
understand value and functionality.
6. What does the INVEST model help ensure for user stories?
A. Technical feasibility
B. High-quality user story characteristics
C. Budget approval
D. Risk reduction
Correct Answer: B. High-quality user story characteristics
INVEST stands for Independent, Negotiable, Valuable, Estimable, Small, and
Testable—qualities of effective user stories.
7. A team reviews what went well and what could be improved after each
iteration. This meeting is called:
A. Sprint planning
B. Daily stand-up
C. Retrospective
D. Backlog refinement
Correct Answer: C. Retrospective
Retrospectives allow teams to evaluate their performance and implement
improvements in future iterations.
8. Which Agile principle focuses on delivering working software frequently?
A. Customer collaboration over contract negotiation
B. Responding to change over following a plan
C. Deliver working product frequently
D. Simplicity—the art of maximizing work not done
Correct Answer: C. Deliver working product frequently
Frequent delivery ensures continuous feedback and higher customer satisfaction.
9. What technique is commonly used to estimate story size collaboratively?
Examination Newest 2025 – 2026 Questions From Past
Papers Actual Exams Complete 100 Questions And
Correct Detailed Answers (Verified Answers) |Already
Graded A+||Brand New!!
Content Covered (Most Tested Areas on the Exam): Agile
Principles and Mindset, Value-Driven Delivery, Stakeholder
Engagement, Team Performance, Adaptive Planning, Problem
Detection and Resolution, Continuous
1. A product owner wants the team to deliver the highest business value early
in the project. Which Agile practice best supports this goal?
A. Developing a full detailed plan at project start
B. Prioritizing the product backlog based on value
C. Assigning tasks based on team member seniority
D. Freezing requirements after sprint one
Correct Answer: B. Prioritizing the product backlog based on value
Agile emphasizes delivering the highest business value first. Prioritizing backlog
items ensures the most valuable features are developed early.
2. During a daily stand-up meeting, what is the primary purpose of team
members sharing updates?
A. Reporting progress to the project sponsor
B. Updating management reports
C. Synchronizing work and identifying impediments
D. Assigning new work to team members
,Correct Answer: C. Synchronizing work and identifying impediments
Daily stand-ups are meant to align the team’s work and quickly surface obstacles
that may block progress.
3. A team notices defects frequently occur late in the sprint. Which Agile
practice helps detect issues earlier?
A. Big design up front
B. Continuous integration
C. Phase-gate reviews
D. Monthly stakeholder meetings
Correct Answer: B. Continuous integration
Continuous integration frequently merges and tests code, allowing issues to be
detected early in development.
4. What is the main responsibility of a Scrum Master?
A. Approving the project budget
B. Managing stakeholder expectations
C. Removing impediments and supporting the team
D. Assigning tasks to developers
Correct Answer: C. Removing impediments and supporting the team
The Scrum Master facilitates Agile practices and removes obstacles so the team
can work efficiently.
5. In Agile projects, requirements are typically documented in the form of:
A. Work breakdown structures
B. Business cases
C. User stories
D. Project charters
Correct Answer: C. User stories
, User stories capture requirements from the user’s perspective and help teams
understand value and functionality.
6. What does the INVEST model help ensure for user stories?
A. Technical feasibility
B. High-quality user story characteristics
C. Budget approval
D. Risk reduction
Correct Answer: B. High-quality user story characteristics
INVEST stands for Independent, Negotiable, Valuable, Estimable, Small, and
Testable—qualities of effective user stories.
7. A team reviews what went well and what could be improved after each
iteration. This meeting is called:
A. Sprint planning
B. Daily stand-up
C. Retrospective
D. Backlog refinement
Correct Answer: C. Retrospective
Retrospectives allow teams to evaluate their performance and implement
improvements in future iterations.
8. Which Agile principle focuses on delivering working software frequently?
A. Customer collaboration over contract negotiation
B. Responding to change over following a plan
C. Deliver working product frequently
D. Simplicity—the art of maximizing work not done
Correct Answer: C. Deliver working product frequently
Frequent delivery ensures continuous feedback and higher customer satisfaction.
9. What technique is commonly used to estimate story size collaboratively?