2026/2027 – a+ GradEd
The purpose of Construction Quality Management is to: - Answer-Achieve the
quality established by properly developed requirements through the combined
responsibility, but seperate efforts of contractpr smd government personnel.
Construction Quality Management is the performance of tasks, which ensure that
construction is performed. - Answer-According to plans and specifications, on
time, within a defined budget and a safe work environment.
The Quality Control Plan: - Answer-Is the foundation upon which quality work is
based and outlines planned quality control procedures.
Tests that are unannounced, randomly performed, and repeat quality control tests
are: - Answer-Quality Assurance tests
If initial review of the quality control plan shows it to be unacceptable: - Answer-
The contractor makes changes before acceptance.
The contractor quality control organization: - Answer-May vary in size depending
on the work being performed at a point in time.
The Quality Control Plan contains: - Answer-Identification of individual quality
quality control personnel, including name, qualifications, assigned duties,
responsibilities and authorities.
, The preconstruction conference and the coordination and mutual understanding
meeting (Navy) are: - Answer-Conducted prior to the commencement of any
physical construction work.
A cumulative list of job deficiencies/rework items can be found in: - Answer-A
deficiency tracking system/reworks items list.
What is a purpose of the coordination and mutual understanding and meeting
(Navy)? - Answer-To review the QC Plan with the contractor.
Which of the following is included in all three phases of the Three Phases of
Control. - Answer-Safety.
Submittals are: - Answer-Necessary to demonstrate that the proposed materials,
etc. are in compliance with the contract.
All submittals for government approval must be provided by the
_________________ in time to allow for the review, approval, procurement,
delivery, and performance of preparatory phase for an item before it is needed for
construction. - Answer-Contractor to the Government
The means for enforcing contract compliance are provided in the: - Answer-
Contract clauses of the contract.