100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4,6 TrustPilot
logo-home
Examen

California Hydroelectric Maintenance Technician Certification Exam Questions And Correct Answers (Verified Answers) Brand New | Guaranteed Pass.

Puntuación
-
Vendido
-
Páginas
27
Grado
A+
Subido en
01-02-2026
Escrito en
2025/2026

California Hydroelectric Maintenance Technician Certification Exam Questions And Correct Answers (Verified Answers) Brand New | Guaranteed Pass. 1. What is the primary purpose of a governor in a hydroelectric turbine system? A. Increase voltage output B. Regulate turbine speed C. Control water temperature D. Protect the generator from overload The governor maintains constant turbine speed by adjusting the flow of water, ensuring frequency stability in the power output. 2. Which component converts mechanical energy into electrical energy in a hydroelectric plant? A. Penstock B. Draft tube C. Generator D. Turbine The generator is driven by the turbine and is responsible for converting rotational mechanical energy into electricity. 3. What is the function of a penstock? A. Houses the generator B. Controls turbine speed C. Stores excess water D. Delivers water to the turbine under pressure The penstock is a pipe that directs pressurized water from the reservoir to the turbine. 4. What device protects the generator from electrical faults? A. Penstock B. Governor C. Exciter D. Circuit breaker Circuit breakers isolate the generator from the grid during faults to prevent equipment damage. 5. What is cavitation in a hydro turbine? A. Electrical short in the stator B. Formation of vapor bubbles in flowing water C. Excessive generator vibration D. Loss of water flow Cavitation causes pitting and damage to turbine blades due to vapor bubble collapse under pressure. 6. Which of the following is a preventive maintenance task? A. Replacing a failed generator B. Lubricating turbine bearings C. Resetting tripped relays D. Responding to alarms Preventive maintenance includes regular tasks like lubrication to avoid future failures. 7. What is the typical frequency of electrical output in the U.S.? A. 25 Hz B. 100 Hz C. 60 Hz D. 50 Hz Hydroelectric generators in the U.S. are synchronized to the standard 60 Hz frequency. 8. Which part of a hydro plant stores potential energy? A. Reservoir B. Turbine C. Transformer D. Draft tube The reservoir holds water at a height, storing potential energy that can be converted to kinetic energy. 9. A Kaplan turbine is best suited for: A. Low head and high flow conditions B. High head and low flow conditions C. Medium head and variable flow D. Constant pressure applications Kaplan turbines are adjustable propeller-type turbines ideal for sites with low head and high water flow. 10. What is the primary cause of generator overheating? A. Low water flow B. High turbine RPM C. Overloading D. Cold ambient temperatures Overloading the generator beyond its rated capacity can cause excessive heat buildup. 11. In predictive maintenance, what tool is used to monitor vibration levels? A. Thermometer B. Vibration analyzer C. Flowmeter D. Multimeter Vibration analyzers help detect misalignment, imbalance, or bearing wear before failure occurs. 12. How is generator cooling typically achieved? A. Water cooling B. Air or hydrogen cooling C. Ice circulation D. Oil circulation Air or hydrogen is often used to dissipate heat generated during electrical production. 13. Which hydro turbine is typically used in high-head applications? A. Pelton B. Kaplan C. Francis D. Francis-Kaplan hybrid Pelton turbines are impulse turbines suitable for high head and low flow conditions. 14. What does a PLC (Programmable Logic Controller) control in a hydro plant? A. Power transmission B. Automated operations of equipment C. Generator rotation speed D. Manual valve opening A PLC automates the control of valves, gates, alarms, and other processes in the plant.

Mostrar más Leer menos
Institución
California Hydroelectric Maintenance Technician
Grado
California Hydroelectric Maintenance Technician










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
California Hydroelectric Maintenance Technician
Grado
California Hydroelectric Maintenance Technician

Información del documento

Subido en
1 de febrero de 2026
Número de páginas
27
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

California Hydroelectric Maintenance Technician Certification
Exam Questions And Correct Answers (Verified Answers) Brand
New 2026-2027 | Guaranteed Pass.



1. What is the primary purpose of a governor in a hydroelectric turbine
system?
A. Increase voltage output
B. Regulate turbine speed
C. Control water temperature
D. Protect the generator from overload
The governor maintains constant turbine speed by adjusting the flow
of water, ensuring frequency stability in the power output.

2. Which component converts mechanical energy into electrical energy in
a hydroelectric plant?
A. Penstock
B. Draft tube
C. Generator
D. Turbine
The generator is driven by the turbine and is responsible for
converting rotational mechanical energy into electricity.

3. What is the function of a penstock?
A. Houses the generator
B. Controls turbine speed
C. Stores excess water
D. Delivers water to the turbine under pressure

, The penstock is a pipe that directs pressurized water from the
reservoir to the turbine.

4. What device protects the generator from electrical faults?
A. Penstock
B. Governor
C. Exciter
D. Circuit breaker
Circuit breakers isolate the generator from the grid during faults to
prevent equipment damage.

5. What is cavitation in a hydro turbine?
A. Electrical short in the stator
B. Formation of vapor bubbles in flowing water
C. Excessive generator vibration
D. Loss of water flow
Cavitation causes pitting and damage to turbine blades due to vapor
bubble collapse under pressure.

6. Which of the following is a preventive maintenance task?
A. Replacing a failed generator
B. Lubricating turbine bearings
C. Resetting tripped relays
D. Responding to alarms
Preventive maintenance includes regular tasks like lubrication to
avoid future failures.

7. What is the typical frequency of electrical output in the U.S.?
A. 25 Hz
B. 100 Hz
C. 60 Hz
D. 50 Hz

, Hydroelectric generators in the U.S. are synchronized to the standard
60 Hz frequency.

8. Which part of a hydro plant stores potential energy?
A. Reservoir
B. Turbine
C. Transformer
D. Draft tube
The reservoir holds water at a height, storing potential energy that
can be converted to kinetic energy.

9. A Kaplan turbine is best suited for:
A. Low head and high flow conditions
B. High head and low flow conditions
C. Medium head and variable flow
D. Constant pressure applications
Kaplan turbines are adjustable propeller-type turbines ideal for sites
with low head and high water flow.



10. What is the primary cause of generator overheating?
A. Low water flow
B. High turbine RPM
C. Overloading
D. Cold ambient temperatures
Overloading the generator beyond its rated capacity can cause
excessive heat buildup.

11. In predictive maintenance, what tool is used to monitor vibration
levels?
A. Thermometer
B. Vibration analyzer
$14.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
ExcelAcademia2026 Chamberlain College Of Nursing
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
2093
Miembro desde
4 año
Número de seguidores
1650
Documentos
8354
Última venta
20 horas hace
EXCEL ACADEMIA TUTORS

At Excel Academia Tutoring, You will get solutions to all subjects in both assignments and major exams. Contact me for assistance. Good luck! Well-researched education materials for you. Expert in Nursing, Mathematics, Psychology, Biology etc. My Work has the Latest & Updated Exam Solutions, Study Guides and Notes (100% Verified Solutions that Guarantee Success)

3.7

343 reseñas

5
141
4
77
3
62
2
20
1
43

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes