Concrete Batch Plant Operator Exam (FDOT)
Questions & 100% Correct Answers (Verified)
Latest Update Grade A+

QUESTIONS AND ANSWERS
Stockpiles of aggregate shall be maintained in a well-drained condition in order to:.
ANSWER - Minimize Free Water Content


Coarse aggregate stockpiles must be sprinkled for at lest how many hours prior to batch for
FDOT?. ANSWER - 24


Free moisture of the aggregate means:. ANSWER - Moister on the surface of an aggregate
that is above and beyond the absorbed moister in the aggregate.


If the moister test is done other than by the cook-out method, how often shall the other
methods be verified?. ANSWER - Each week


For drill shaft concrete, the quantity of cement replaced with fly ash shall be:. ANSWER -
33 thru 37%


In concrete, which material has a specific gravity of one?. ANSWER - Water


What is the air content range for all classes of structural concrete except Class IV Shaft?.
ANSWER - 1.00 thru 6.00%


When can unmetered water be added to the concrete?. ANSWER - Not at all.


Do not allow the total number of revolution at mixing speed to exceed:. ANSWER - 160
Revolutions

, After all materials have been charged into the transit mixer drum, the concrete must be
mixed at how many revolutions at the plant before leaving for the project?. ANSWER - 70
to 100


When the water meters / scales are calibrated, prior to production, at what frequency
should they be checked there after?. ANSWER - 3 moths


To what accuracy should the scales for weighing cement , pozzolan, slag and aggregates at
the plant be maintained. ANSWER - 0.5% of maximum load normally handled


For concrete containing a water-reducing retarding admixture, in an agitator truck, the
maximum time for depositing the concrete shall not exceed:. ANSWER - 90 minutes


If a load of concrete has been rejected due to excessive slump, the concrete may remain in
the transporting vehicle to reduce the slump.. ANSWER - Is not allowed.


Who places the orders for concrete with the producer?. ANSWER - The contractor


The minimum normal sampling frequency for the chloride content of structural concrete
is:. ANSWER - 1 per design mix in use from the first day of production and every 30
calendar days or less thereafter.


In what moister condition are the aggregates on the approved concrete mix designs?.
ANSWER - SSD condition


The specific gravity of an aggregate is the ratio of its unit weight to the weight of an equal
absolute volume of:. ANSWER - Water


What is the weight of a bag of Portland cement in the USA?. ANSWER - 94 lbs


What is the maximum concrete temperature allowed when using a hot weather design
mix?. ANSWER - 100 degrees F

Información del documento

Subido en
28 de enero de 2026
Número de páginas
5
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$11.39

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Vendido
8
Seguidores
0
Artículos
1069
Última venta
1 mes hace


Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes