1. A programs flyaway cost covers the _______ using ______ appropriation funds-
: Prime mission equipment and procurement
2. Identify the missing steps in the 12 step life cycle sustainment plan process model: 1. Identify/refine financial enablers
2. Establish/ refine product support arrangements
3. Implement and asses
4. Integrate warfighter requirements and support
5. Form the product support management IPT
6. Baseline the system
7. Identify/refine performance outcomes
8. Business case analysis
9. Product support value analysis
10. Determine Support Method
11. Design product support integrator
12. Identify product support provider
3. This document states that the life cycle support plan (LCSP) will be updated at each decision point to reflect the increase
the maturity of the PSS any changes in the corresponding psp current risk and any cost reduction activity: DODI 5000.91
4. ____ should be included in the PBL contract to include the target level of performance: Incentives
5. The SMART criteria for this metrics stand for this: Specific, measurable, attainable, relevant, and timely
6. Approximately _____ of software life cycle costs are incurred later in the programs life cycle: 70%
1/7
, 7. These statements reflect DOD guidance and best practices regarding soft-
ware acquisition: Develop software systems architecture that supports open systems and select a program language that
influences overall life cycle costs, risks, and the potential for interoperability
8. This appraisal should be part of the best value selection process regarding selecting a mature software developer:
Cybersecurity maturity model certification (CMMC)
9. Software used from this source will increase the configuration management challenges: Third party or commercial
10 These are the three primary benefits of using COTS components in system
design: Reduces development time, allows faster insertion of new technology, lowers life cycle cost by taking advantage
of the more readily available commercial industrial base
11. Requirements for interoperability testing include these: Assesses and certifies full end to end interoperability of
systems, joint interoperability certifications are mandatory for all programs with relevant data exchange and
interoperability and supportability memo is required for CDD validation
12. Modifications to these material solution approaches are subject to additional T&E: COTS and non-developmental
items
13. This approach supports but does not replace the need for developmental and operational testing: Modeling and
simulation
14. This type of testing verifies the design and manufacturing process: Production
Quality Testing (PQT)
15. This type of testing assesses performance of components, subsystems and systems under relevant environmental
parameters: Environmental
16. The work breakdown structure becomes an important tool in systems analysis and control within this process:
Systems engineering process