and Answers (Latest Update 2026)
- Chapter 1
There are no two projects in construction that are identical (from
the contractor's point of view). -
correct answer ✅True
Every construction project needs a CPM schedule -
correct answer ✅False
Planning and scheduling are two names for the same function -
correct answer ✅False
The maintenance of a large office building is considered a project -
correct answer ✅False
The renovation of a large office building is considered a project -
correct answer ✅True
Project control deals only with the money aspect of the project -
correct answer ✅False
, CNST 304 Chapters 1-5 Exam Questions
and Answers (Latest Update 2026)
Projects in a portfolio are necessarily related. -
correct answer ✅False
Projects in a program are necessarily related. -
correct answer ✅True
All programs have specific limited lifespan -
correct answer ✅False
The maintenance of city bridges can be a program. -
correct answer ✅True
Every program has a starting point and a finishing point. -
correct answer ✅False
Project control is a function that takes place: -
correct answer ✅While construction is going on
-
correct answer ✅Chapter 2