Data has been collected and a P chart drawn. A ______ can also be
constructed using the same data collected for the P chart as long as the
subgroups are the same size. - ANSWERS-NP Chart
During the first shift, 1000 inspections are made of widgets and 10
nonconforming units are found during the shift there was 10,000 widgets
made. What is the fraction of nonconforming? - ANSWERS-.01
possible a P chart should be developed and used with a constant subgroup
size. In - ANSWERS-True
When constructing a ______ chart the general procedures that apply to
variable control charts also apply to the _______. - ANSWERS-P Chart
Whenever possible, NP charts should be developed and used with a constant
subgroup size even though at times different subgroup sizes must be used. -
ANSWERS-False
Supervisors of activities and especially the chief executive officer should be
evaluated by a chart for non-conforming units. - ANSWERS-True
The term attributes as used in quality, refers to those quality characteristics
that conform to specifications or do not conform to specifications. -
ANSWERS-True
, Reliability is the probability that a product will perform its intended function
satisfactorily for prescribed life under certain stated environmental
conditions. - ANSWERS-True
Reliability and failure rate are synonymous. - ANSWERS-False
The production process is the second most important aspect of reliability
where the emphasis should be placed on those components that are _______.
By focusing on this aspect the probability of failure will decrease. -
ANSWERS-least reliable
Attributes are used whenever measurements are possible. - ANSWERS-False
In most cases knowledge of the number of units that are nonconforming
provides management with information on whether to release an order. -
ANSWERS-False
A proportion, P, chart shows the proportion nonconforming in a sample or a
subgroup. The proportion is expressed as a ______. (Choose all that apply) -
ANSWERS-fraction
percent
A _____is more user-friendly for an operator than a P chart. - ANSWERS-NP
chart
If a point is located outside the upper control limit in a P chart the______. -
ANSWERS-assignable cause for that point must be determined and a revised
central line and control limits must be established
The subgroup size of the P chart______. - ANSWERS-may be constant or
variable