WITH SOLUTIONS GRADED A+
◉ The project delivery method where the GC is responsible for much of
the design is ___. Answer: design-build
◉ The project delivery method used for change orders or small projects
is ___. Answer: time and material
◉ RFP typically means ___. Answer: request for pricing/proposal
◉ Costs for additional items not covered in the original construction
contract are authorized by ___. Answer: change orders
◉ CAD is the acronym for ___. Answer: computer-aided drafting
◉ Pages within a set of prints are numbered according to the type and
convention. What is an example of a naming convention found within a
set of prints? Answer: fire protection
◉ BIM is the acronym for ___. Answer: Building Information Modeling
, ◉ Drawing standards for symbols have been developed by ___. Answer:
ANSI
◉ What kind of notes relate to an entire sheet or set of drawings?
Answer: general notes
◉ What kind of notes relate to specific items on a drawing? Answer: key
notes
◉ What are the scale types found on drawings? Answer:
Architectural/Engineering
◉ 1″ equals 50 feet is what type of scale? Answer: Engineering and
Civil
◉ 1/4″ equals 1 foot is what type of scale? Answer: Architectural
◉ Which of the following is the spec division for electrical? Answer: 26
◉ Which of the following is the spec division for communications?
Answer: 27