Activity - Correct Answer -An assignable element of work within a project. Syn: task.
Critical Path - Correct Answer -The longest sequence of activities through a project plan. It
defines the project duration.
Earliest Finish Time - Correct Answer -The soonest a project activity can be completed
based on predecessor completion times and activity duration.
Earliest Start Time - Correct Answer -The soonest a project activity can begin based on
predecessor completion times.
Gantt Chart - Correct Answer -A planning tool, composed of horizontal lines that represent
activity durations, used for the management of a project.
Latest Finish Time - Correct Answer -The last point at which a project activity must be
completed in order to not delay the project completion.
Latest Start Time - Correct Answer -The last point at which a project activity must begin in
order to not delay the project completion.
Network Diagram - Correct Answer -A graphical tool that shows activity dependencies in a
project.
Project - Correct Answer -A (typically) one-time endeavor with a specific objective to be
met within predetermined time and dollar limitations and that has been assigned for planning
and execution.
1
QUESTIONS WITH 100% CORRECT
ANSWERS
Activity - Correct Answer -An assignable element of work within a project. Syn: task.
Critical Path - Correct Answer -The longest sequence of activities through a project plan. It
defines the project duration.
Earliest Finish Time - Correct Answer -The soonest a project activity can be completed
based on predecessor completion times and activity duration.
Earliest Start Time - Correct Answer -The soonest a project activity can begin based on
predecessor completion times.
Gantt Chart - Correct Answer -A planning tool, composed of horizontal lines that represent
activity durations, used for the management of a project.
Latest Finish Time - Correct Answer -The last point at which a project activity must be
completed in order to not delay the project completion.
Latest Start Time - Correct Answer -The last point at which a project activity must begin in
order to not delay the project completion.
Network Diagram - Correct Answer -A graphical tool that shows activity dependencies in a
project.
Project - Correct Answer -A (typically) one-time endeavor with a specific objective to be
met within predetermined time and dollar limitations and that has been assigned for planning