MGMT 404 Midterm Questions and Verified
Answers
Emphasizing areas of agreement and deemphasizing areas of non-agreement
represents which type of conflict resolution mode?
a. Confrontation
b. Compromise
c. Forcing
d. Smoothing— Correct Answer: D
Activates with zero-time duration are called:
a. Low-slack activities
b. No-slack activities
c. Milestone activities
d. Special activities— Correct Answer: C
Which of the following is false concerning the critical path in a network?
a. It is the longest path in the network
b. It is the shortest amount of time in which the project can be completed
c. It is that contains the greatest number of activities
d. It is the path where each activity has zero slack— Correct Answer: C
, Which of the following schedule compression techniques usually requires adding
more resources to each work package that is being compressed?
a. Overtime
b. Crashing
c. Outsourcing
d. Descoping— Correct Answer: B
Of the following, which is the logical order of the project management processes?
a. Initiating, planning, monitoring and controlling, executing, closing
b. Initiating, planning, executing, monitoring and controlling, closing
c. Planning, initiating, monitoring and controlling, executing, closing
d. Planning, initiating, executing, closing, monitoring and controlling— Correct
Answer: B
All of the following are true statements about the project life cycle, except for
which one?
a. The project life cycle defines the work to be done in each phase of the project
b. The project life cycle defines the deliverables that each phase will create
c. The project life cycle defines who involved in each phase
d. The project life cycle defines how much each phase will cost— Correct Answer:
D
What is the only tool and technique used during scope verification?
Answers
Emphasizing areas of agreement and deemphasizing areas of non-agreement
represents which type of conflict resolution mode?
a. Confrontation
b. Compromise
c. Forcing
d. Smoothing— Correct Answer: D
Activates with zero-time duration are called:
a. Low-slack activities
b. No-slack activities
c. Milestone activities
d. Special activities— Correct Answer: C
Which of the following is false concerning the critical path in a network?
a. It is the longest path in the network
b. It is the shortest amount of time in which the project can be completed
c. It is that contains the greatest number of activities
d. It is the path where each activity has zero slack— Correct Answer: C
, Which of the following schedule compression techniques usually requires adding
more resources to each work package that is being compressed?
a. Overtime
b. Crashing
c. Outsourcing
d. Descoping— Correct Answer: B
Of the following, which is the logical order of the project management processes?
a. Initiating, planning, monitoring and controlling, executing, closing
b. Initiating, planning, executing, monitoring and controlling, closing
c. Planning, initiating, monitoring and controlling, executing, closing
d. Planning, initiating, executing, closing, monitoring and controlling— Correct
Answer: B
All of the following are true statements about the project life cycle, except for
which one?
a. The project life cycle defines the work to be done in each phase of the project
b. The project life cycle defines the deliverables that each phase will create
c. The project life cycle defines who involved in each phase
d. The project life cycle defines how much each phase will cost— Correct Answer:
D
What is the only tool and technique used during scope verification?