m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
m0
Time Management Plan _ANSWER-Explains how the schedule will be developed,
m0 m0 m0 m0 m0 m0 m0 m0 m0
monitored and controlled.
m0 m0 m0
Configuration Management Plan _ANSWER-Documents how the project team and
m0 m0 m0 m0 m0 m0 m0 m0
stakeholders will keep track of the versions of project documents to ensure that the
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
most up-to-date document is in use.
m0 m0 m0 m0 m0 m0
Change Management Plan _ANSWER-Documents how changes to the project outcomes
m0 m0 m0 m0 m0 m0 m0 m0 m0
will be managed, approved, implemented, and monitored.
m0 m0 m0 m0 m0 m0 m0
Process Improvement Plan _ANSWER-Describes how the processes and procedures used
m0 m0 m0 m0 m0 m0 m0 m0 m0
on the project will be evaluated to ensure that the most efficient methods are
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
implemented.
m0
Requirements Management Plan _ANSWER-Documents how the customer and m0 m0 m0 m0 m0 m0 m0
stakeholder requirements will be identified, integrated to the project scope, tracked
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
throughout the project, and verified at closure.
m0 m0 m0 m0 m0 m0 m0
monitoring and controlling _ANSWER-It is central to the PM's role to know the status of the
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
project work (monitor) and take action as needed to ensure the project plan is
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
completed as planned (control).
m0 m0 m0 m0
lessons learned _ANSWER-have great value to the project organization because they
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
provide guidance for future projects.
m0 m0 m0 m0 m0
,The triple constraint concept _ANSWER-It is not possible to change any one side of a
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
triangle without affecting the other two characteristics
m0 m0 m0 m0 m0 m0 m0
The triple constraints are: _ANSWER-Time, Cost, Scope
m0 m0 m0 m0 m0 m0
project scope _ANSWER-is, simply put, what the result of the project is desired to be.
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
statement of work (SOW) _ANSWER-It defines the product of the project.
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
Scope creep _ANSWER-occurs when there are any—but particularly small—incremental
m0 m0 m0 m0 m0 m0 m0 m0
additions to the project scope that are not subject to the formal scope change process.
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
critical path _ANSWER-is defined as the path with the longest duration from the start of the
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
project to its completion.
m0 m0 m0 m0
Float time/slack time _ANSWER-is the amount of time an activity can be delayed without
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
affecting the completion date of the project.
m0 m0 m0 m0 m0 m0 m0
Administrative activities _ANSWER-during the project closing phase include performancem0 m0 m0 m0 m0 m0 m0 m0
report preparation, return of assets to the sponsoring organizations, archival of records,
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
and documentation of lessons learned.
m0 m0 m0 m0 m0
Customer delivery activities _ANSWER-project closing phase include returning excess
m0 m0 m0 m0 m0 m0 m0 m0
materials, reconciling accounts payable, and preparing required financial reports.
m0 m0 m0 m0 m0 m0 m0 m0 m0
Milestones _ANSWER-in a project schedule identify critical events and other activities that
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
must be performed by specific dates before the project may proceed.
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
Iterative planning processes _ANSWER-allows the project to move forward in phases when
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
not enough information is known to plan the entire project
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
common components of project scope statements _ANSWER-Project constraints, project
m0 m0 m0 m0 m0 m0 m0 m0
acceptance criteria and technical requirements
m0 m0 m0 m0 m0
Project schedule _ANSWER-A timeline that specifies when the project begins and when it is
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
supposed to end
m0 m0 m0
Project cost _ANSWER-The sum total of all expenses directly charged to the project
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
Traditional project management methods _ANSWER-PERT, CPM, critical chain, waterfall,
m0 m0 m0 m0 m0 m0 m0 m0
and PRINCE2
m0 m0
Project evaluation and review technique (PERT) _ANSWER-was developed in the 1950s to
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
support the U.S. Navy's Polaris missile project. It uses a statistical approach to
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
estimate the time that will be required to complete project work activities.
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
, Critical path method (CPM) _ANSWER-was developed for the DuPont Corporation to help
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
with projects in their manufacturing plants. It used for estimating project activity
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
durations but CPM assumes that the estimates do not vary and time can be reliably
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
estimated.
m0
Critical chain project management (CCPM) _ANSWER-focuses on managing the
m0 m0 m0 m0 m0 m0 m0 m0
uncertainties of a project. It assumes that resources available to complete the project
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
are in limited supply and it specifically plans to ensure resource availability.
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
Waterfall _ANSWER-is a traditional practice which found its best use in software and
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
hardware development.
m0 m0
Extreme _ANSWER-addresses issues of extraordinary uncertainty or complexity.
m0 m0 m0 m0 m0 m0 m0
PRINCE2 _ANSWER-is a highly structured project management method which focuses on
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
the specification of the outputs rather than the coordination of activities
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
duration _ANSWER-describe the number of time periods required to complete some
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
portion of the work.
m0 m0 m0 m0
activities _ANSWER-are the starting point for developing the project schedule because
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
they identify specific work that will need to occur in order to execute the project.
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
Deterministic duration estimation techniques _ANSWER-are appropriate when the activity
m0 m0 m0 m0 m0 m0 m0 m0
durations are very predictable.
m0 m0 m0 m0
Probabilistic duration estimation techniques _ANSWER-are used when there is uncertainty
m0 m0 m0 m0 m0 m0 m0 m0 m0
in how long an activity will take.
m0 m0 m0 m0 m0 m0 m0
one-point estimate _ANSWER-requires that the team expert provide a reliable estimate of
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
the time necessary to complete the activity.
m0 m0 m0 m0 m0 m0 m0
triangular distribution _ANSWER-Activity Duration=O+M+P/3
m0 m0 m0
beta distribution _ANSWER-uses the three estimates (optimistic, most likely, and
m0 m0 m0 m0 m0 m0 m0 m0 m0
pessimistic) but places emphasis on the most likely estimate. Activity
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
Duration=O+4M+P/6
m0
learning curves _ANSWER-that as a person repeats a task, the time required to complete
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
the task decreases.
m0 m0 m0
Other factors that can influence the impact of learning curves _ANSWER-The complexity of
m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0 m0
the activity
m0 m0
The level of human input required The
m0 m0 m0 m0 m0 m0
duration of the activity
m0 m0 m0 m0