WGU C722 PROJECT MANAGEMENT - STUDY GUIDE / 400+ ACTUAL EXAM QUESTIONS AND ANSWERS (A+ GUIDE SOLUTION) NEWEST 2026/2027

Institución
WGU C722 PROJECT MANAGEMENT
Grado
WGU C722 PROJECT MANAGEMENT











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
WGU C722 PROJECT MANAGEMENT
Grado
WGU C722 PROJECT MANAGEMENT

Información del documento

Subido en
14 de enero de 2026
Número de páginas
131
Escrito en
2025/2026
Tipo
Examen
Contiene
Desconocido

Temas

Vista previa del contenido

WGU C722 PROJECT MANAGEMENT -
STUDY GUIDE / 400+ ACTUAL EXAM
QUESTIONS AND ANSWERS (A+ GUIDE
SOLUTION) NEWEST 2026/2027




1. Question:
What is the primary difference between a project and ongoing operations?
A) Projects have a defined beginning and end, while operations are
continuous
B) Projects are always larger in scale than operations
C) Operations require more planning than projects
D) Projects are managed by different departments than operations
Answer: A
Rationale: Projects are temporary endeavors with a definite start and end
date, created to produce a unique product, service, or result. Operations
are ongoing, repetitive activities that sustain the organization.




2. Question:

,Which document formally authorizes a project and provides the project
manager with authority to apply organizational resources?
A) Project Management Plan
B) Business Case
C) Project Charter
D) Scope Statement
Answer: C
Rationale: The project charter is issued by the project sponsor and
formally authorizes the project's existence, giving the project manager
authority to use organizational resources for project activities.




3. Question:
The "triple constraint" of project management traditionally includes all
EXCEPT:
A) Scope
B) Time
C) Cost
D) Quality
Answer: D
Rationale: The traditional triple constraint consists of scope, time, and
cost. Quality is often considered a fourth constraint but is not part of the
original triple constraint model.




4. Question:

,What is the correct order of processes in the project management life
cycle?
A) Planning, Initiating, Executing, Monitoring & Controlling, Closing
B) Initiating, Planning, Executing, Monitoring & Controlling, Closing
C) Initiating, Executing, Planning, Monitoring & Controlling, Closing
D) Planning, Executing, Initiating, Monitoring & Controlling, Closing
Answer: B
Rationale: The standard project management process groups follow this
sequence: Initiating, Planning, Executing, Monitoring & Controlling, and
Closing.




5. Question:
In which organizational structure does the project manager have the least
authority?
A) Projectized
B) Strong Matrix
C) Balanced Matrix
D) Functional
Answer: D
Rationale: In a functional organization, project managers have little to no
formal authority as team members report to functional managers. Project
managers in functional organizations typically have a coordinator or
expeditor role.




6. Question:

, A Work Breakdown Structure (WBS) is primarily used for:
A) Assigning team members to tasks
B) Defining the total scope of the project
C) Creating the project schedule
D) Estimating project costs
Answer: B
Rationale: The WBS is a hierarchical decomposition of the total scope of
work to be carried out by the project team. It's a scope management tool,
not primarily for scheduling, cost estimating, or resource assignment.




7. Question:
What is the critical path in a project schedule?
A) The path with the most activities
A) The path with the fewest activities
C) The longest path through the network diagram
D) The path with the highest risk activities
Answer: C
Rationale: The critical path is the longest duration path through a network
diagram, determining the shortest possible project duration. Any delay on
the critical path delays the entire project.




8. Question:
If a task has an optimistic estimate of 10 days, pessimistic estimate of 20
days, and most likely estimate of 12 days, what is the PERT estimate?
A) 12 days
$23.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Bestnursesteve Chamberlain College Of Nursing
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
553
Miembro desde
1 año
Número de seguidores
65
Documentos
5429
Última venta
9 horas hace
TEACH ME TO

TEACH ME TO I HEIP STUDENTS WITH ALL TYPE OF EXAMZ LIKE NGN,ATI,HESI,PN COMPREHENSION., FIREFIGHTER ,ECONOMICS .ENGLISH,SPANISH.MATHEMATICS .......TO SCORE A+ AND ALSO TO ASSIST IN ANY EXAM POSSIBLE

4.8

1514 reseñas

5
1356
4
90
3
27
2
14
1
27

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes