100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4,6 TrustPilot
logo-home
Examen

AIC Exam Questions and Answers (100% Correct Answers) Already Graded A+

Puntuación
-
Vendido
-
Páginas
48
Grado
A+
Subido en
11-01-2026
Escrito en
2025/2026

AIC Exam Questions and Answers (100% Correct Answers) Already Graded A+

Institución
AIC
Grado
AIC











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
AIC
Grado
AIC

Información del documento

Subido en
11 de enero de 2026
Número de páginas
48
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

For Expert help and assignment handling,
1





AIC Exam Questions and Answers (100%
Correct Answers) Already Graded A+
5 days Ans: A project schedule has been updated. The activity
placement of spread footing concrete was originally scheduled to begin
as early as day 10. The activity duration is 4 days. The actual start day
was day 12. The original schedule had calculated total float of 7 days for
this activity. The recalculated total float for the activity, when updated,
© 2026 Assignment Expert




would be


a. 2 days b. 5 days c. 6 days d. 9 days
Guru01 - Stuvia




Complete project per contract Ans: The purpose of retainage is to
encourage the general contractor to?


a. Submit payment request on time b. Complete project per contract


13 Ans: . A 'place concrete' activity requires the placement of 2080
cubic yards. If the individual production rate is 2 cubic yards per work
hour per person, with a 10-person crew and 8 hour workday, how many
days are needed to complete this activity?


a. 13 b. 26 c. 104 d. 130


Plan quantity divided by daily production rate Ans: What method is used
to calculate activity duration?


a. Daily production rate divided by plan quantity b. Plan quantity
divided by crew rate c. Plan quantity divided by daily production rate d.
Plan quantity dived by labor unit cost

,For Expert help and assignment handling,
2




Contractors proposed breakdown of the project cost Ans: Which of the
following can be identified from the initial schedule of values?


a. Vendors working on the project b. Contractors proposed breakdown
of the project cost c. Profit margin of the applicant d. Quality of work in
place


HVAC subcontractor and all other affected subcontractors Ans: The
architect has approved the rerouting of an HVAC through concrete
slabs in a building. To insure that activities are coordinated, a meeting
© 2026 Assignment Expert




should be called by the field supervisor and the


a. HVAC subcontractor only b. HVAC subcontractor and all other
Guru01 - Stuvia




subcontractors c. HVAC subcontractor and all other affected
subcontractors d. HVAC subcontractor and the architect engineer


20.3 Ans: Concrete to be poured for 10 footings are 5 feet wide by 5 feet
long by 2 feet deep. How many cubic yards of concrete should the
estimate be for this pour, using a 10%waste factor.


a. 14.8 b. 16.3 c. 18.5 d. 20.3


Contour lines and elevations Ans: A topographical map is a drawing
showing?


a. Subsurface soil conditions b. A general profile view of the site c.
Contour lines and elevations d. Cross sections along the length of the
project.


Concrete is in tension Ans: The location of reinforcing steel used in a
concrete member should be placed where?

,For Expert help and assignment handling,
3




a. Shear is minimal b. Concrete is in tension c. Concrete is in compression
d. Center axis is located.


Notify general contractors superintend of problem Ans: The owner's rep
observed substandard drywall patches on a general contractor's
renovation project. Which of the following should be the representative's
first course of action?


a. Save items for punch list b. Notify drywall finisher of the problem c. Tell
painter not to accept patched walls. d. Notify general contractors
© 2026 Assignment Expert




superintend of problem.


The contractor should request a 5-day time extension due to the rain,
Guru01 - Stuvia




and should be compensated for the 4 days compensable delay by the
owner Ans: A contract for a project contains a liquidated damages
clause. The project is under compensable delay for 4 days. In addition,
rain caused another 5-day non-compensable delay. How should the
delay be handled?


a. The contractor should assume the costs of the 5-day delay less the
cost owed by the owner for the 4 day delay b. Since both delays have
caused an explanation of the completion date, contractor should be
liable to the owner for the costs for a total delay of 9 days. c. The
contractor should request a 5-day time extension due to the rain, and
should be compensated for the 4 days compensable delay by the
owner d. The costs delay is overridden by the delay due to the rain. The
owner is relieved of compensable delay, and the contractor should
assume the costs of 5 days delay


Completed training card Ans: Which of the following is required for an
employee to operate a powder operated tool?

, For Expert help and assignment handling,
4




a. Drivers licence b. Contract terms c. Completed training card d. Osha
ten hour card


Unknown conditions Ans: A contingency fund would be used for?


a. Unknown conditions b. Stipulated price increase c. Purchase of
backup equipment d. Concrete quantities taken from the drawings


Material suppliers Ans: The uniform construction code is an area of
© 2026 Assignment Expert




a. Material suppliers b. Subcontractor services c. Federal subcontractors
d. Contract in excess of 1 million dollars
Guru01 - Stuvia




Variance in progress of the project Ans: The baseline schedule or target
should be maintained in order to analyze the?


a. Variance in progress of the project b. Float time is the current
schedule c. Critical path d. Correlative effect of the "leach"


Value engineering Ans: A project bid comes in over budget. The
architect might request proposal from some, or all of the bidders to
suggest ways to reduce costs without degrading the quality of the
project. What term describes this accurately?


a. Value engineering b. Cost engineering c. Price engineering d. Quality
control


3ft Ans: A portable ladder is being set up. The distance between the
ground and the first floor is 16ft. according to OSHA, what is the minimum
ladder extension required above the area?
$14.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Graders Chamberlian School of Nursing
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
503
Miembro desde
2 año
Número de seguidores
167
Documentos
26778
Última venta
2 horas hace
Study Smart

Your one-stop resource for high-quality, exam-focused study materials. Here, you'll find expertly crafted summaries, past exam papers, notes, and assignments tailored to help you succeed in your courses. Every document is written with clarity, accuracy, and exam performance in mind—saving you hours of studying and helping you boost your grades. ✅ Clear and well-structured content ✅ Covers key exam topics and common questions ✅ Trusted by students for academic success ✅ Instant downloads and affordable prices Whether you're cramming for finals or just staying ahead in class, my materials are designed to make your studying smarter, not harder. Take a look around and get the edge you need!

Lee mas Leer menos
3.8

121 reseñas

5
54
4
26
3
21
2
4
1
16

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes