According to AHERA, to complete a response action of a non-NESHAP size project,
how many samples must be taken with results of what? - ANSWER-5 samples taken
inside with results of each <0.0 f/cc
According to ASHERA, how many air samples must be taken for final clearance for
NESHAP size project? - ANSWER-13 samples (5 inside, 5 outside, 2 fields blanks , one
sealed blank)TEM
According to OSHA construction standard, fall protection is required at working at or
above - ANSWER-6 feet
According to OSHA, the contractor must establish a medical surveillance program for -
ANSWER-All employees who are issued respirators
Aggressive air sampling techniques are used to - ANSWER-Make the conditions the
worst they can be
Aggressive air sampling would be used: - ANSWER-Following visual clearance, in
preparation for final air clearance according to AHERA protocol
AHERA is for - ANSWER-Public schools K-12
All employees must carry - ANSWER-Workers compensation coverage
An injured employee on workman's compensation will receive: - ANSWER-A
percentage of there average annual pay
Asbestos may cause harm to humans when it is: - ANSWER-Inhaled
Asbestos signs should all have: - ANSWER-DANGER
ASHARA regulations are training requirements for asbestos work in: - ANSWER-
Schools, public buildings, and commercial buildings
Bulk samples are typically analyzed using: - ANSWER-Polarized Light
Microscopy(PLM)
Bulk samples are typically analyzed: - ANSWER-Using polarized light microscopy
Chest XRays must be evaluated by what class reader? - ANSWER-Class B
Class 1 asbestos work activities involve the removal of repair of: - ANSWER-Surfacing
and thermal system insulation ACM and PACM
, Encapsulation is - ANSWER-The use of paint or glue to hold down any exposed friable
asbestos fibers
Exposure minoring is the responsibility of the: - ANSWER-Competent person
Friable ACM is any material that can be: - ANSWER-Crushed, pulverized, reduced to
powder by hand pressure when dry
Heat stress can be avoided by - ANSWER-Resting in cool area and drinking water
during breaks
How many air changes (minimum) are required per hour in an asbestos removal
containment area - ANSWER-4
If a contractor has 10 workers on a job lasting 15 days, how many disposal suits will
likely be required for that project - ANSWER-600
If worker exposure sampling is required, how many workers must wear sampling
pumps? - ANSWER-One per task per shift
In Maryland "project notification" signs are required for ________ projects - ANSWER-
NESHAP renovations and demolitions
In Maryland, protective clothing must be: - ANSWER-Disposable
In Maryland, the asbestos project notification must be posted when and where? -
ANSWER-Three days prior to any asbestos project, at all entrances and exits from the
work site.
In what jurisdiction do individuals need an asbestos supervisor or working linsense -
ANSWER-Need a license everywhere
Initial worker exposure air samples are collected: - ANSWER-To predict what future
exposures should be on this project
Laboratories that perform PLM and TEM must be accredited by - ANSWER-National
Voluntary Laboratory Accreditation Program
Minimum respiratory protection on a class 1 asbestos project with no NEA - ANSWER-
Full face air purifying respirator
NESHAP regulations provide definitions for - ANSWER-Renovations, Adequately Wet,
and Demolitions
According to AHERA, to complete a response action of a non-NESHAP size project,
how many samples must be taken with results of what? - ANSWER-5 samples taken
inside with results of each <0.0 f/cc
According to ASHERA, how many air samples must be taken for final clearance for
NESHAP size project? - ANSWER-13 samples (5 inside, 5 outside, 2 fields blanks , one
sealed blank)TEM
According to OSHA construction standard, fall protection is required at working at or
above - ANSWER-6 feet
According to OSHA, the contractor must establish a medical surveillance program for -
ANSWER-All employees who are issued respirators
Aggressive air sampling techniques are used to - ANSWER-Make the conditions the
worst they can be
Aggressive air sampling would be used: - ANSWER-Following visual clearance, in
preparation for final air clearance according to AHERA protocol
AHERA is for - ANSWER-Public schools K-12
All employees must carry - ANSWER-Workers compensation coverage
An injured employee on workman's compensation will receive: - ANSWER-A
percentage of there average annual pay
Asbestos may cause harm to humans when it is: - ANSWER-Inhaled
Asbestos signs should all have: - ANSWER-DANGER
ASHARA regulations are training requirements for asbestos work in: - ANSWER-
Schools, public buildings, and commercial buildings
Bulk samples are typically analyzed using: - ANSWER-Polarized Light
Microscopy(PLM)
Bulk samples are typically analyzed: - ANSWER-Using polarized light microscopy
Chest XRays must be evaluated by what class reader? - ANSWER-Class B
Class 1 asbestos work activities involve the removal of repair of: - ANSWER-Surfacing
and thermal system insulation ACM and PACM
, Encapsulation is - ANSWER-The use of paint or glue to hold down any exposed friable
asbestos fibers
Exposure minoring is the responsibility of the: - ANSWER-Competent person
Friable ACM is any material that can be: - ANSWER-Crushed, pulverized, reduced to
powder by hand pressure when dry
Heat stress can be avoided by - ANSWER-Resting in cool area and drinking water
during breaks
How many air changes (minimum) are required per hour in an asbestos removal
containment area - ANSWER-4
If a contractor has 10 workers on a job lasting 15 days, how many disposal suits will
likely be required for that project - ANSWER-600
If worker exposure sampling is required, how many workers must wear sampling
pumps? - ANSWER-One per task per shift
In Maryland "project notification" signs are required for ________ projects - ANSWER-
NESHAP renovations and demolitions
In Maryland, protective clothing must be: - ANSWER-Disposable
In Maryland, the asbestos project notification must be posted when and where? -
ANSWER-Three days prior to any asbestos project, at all entrances and exits from the
work site.
In what jurisdiction do individuals need an asbestos supervisor or working linsense -
ANSWER-Need a license everywhere
Initial worker exposure air samples are collected: - ANSWER-To predict what future
exposures should be on this project
Laboratories that perform PLM and TEM must be accredited by - ANSWER-National
Voluntary Laboratory Accreditation Program
Minimum respiratory protection on a class 1 asbestos project with no NEA - ANSWER-
Full face air purifying respirator
NESHAP regulations provide definitions for - ANSWER-Renovations, Adequately Wet,
and Demolitions