SCM 421 Exam 3 Questions With Correct
Answers

Production |planning |and |control |systems |are |comprised |of |these |2 |activities: |- |CORRECT |
ANSWER✔✔-1. |Planning |and |control |of |materials |

"Materials |management"

2.Planning |and |control |of |capacities |

"Capacity |planning"



Materials |Management |- |CORRECT |ANSWER✔✔-supports |the |transformation |of |raw |materials |
and |component |parts |into |shipped |or |finished |goods



Capacity |Planning |- |CORRECT |ANSWER✔✔-The |process |of |determining |how |much |capacity |is |
needed |(and |when) |in |order |to |produce |in |the |future



What |materials |do |we |buy? |- |CORRECT |ANSWER✔✔--Raw |Materials |

-Purchased |Parts |and |Components



Raw |Materials |- |CORRECT |ANSWER✔✔-Materials |not |yet |committed |to |production

ex: |"commodities" |such |as |crude |oil, |coal, |paperboard. |paper, |lumber, |copper, |wheat, |cotton



Purchased |Parts |and |Components |- |CORRECT |ANSWER✔✔-Includes |semi-finished |items |that |
will |be |further |processed |or |finished |materials |that |will |become |components |of |finished |goods



MRO |stands |for |- |CORRECT |ANSWER✔✔-maintenance, |repair, |and |operating |(suppliers)

,Maintenance |- |CORRECT |ANSWER✔✔-Items |we |expect |to |periodically |replace |in |a |piece |of |
equipment, |overtime |parts |wear |and |are |replaced

-original |manufacturer |expects |to |supply |these |parts |during |the |life |of |the |equip.

-application |or |renewal |(lubricant |and |coolants)

-periodic |maintenance |ensures |longevity

-less |expensive

ex: |car |getting |an |oil |change



Repair |- |CORRECT |ANSWER✔✔--should |be |infrequent

-suggests |the |unexpected

-having |to |deal |with |equipment |that |wasn't |expected |to |fail

-sudden/urgent



Operating |supplies |- |CORRECT |ANSWER✔✔-Parts |of |the |end |items |, |essential |for |production, |
BUT |unit |value |or |size |is |too |small |to |plan |or |control |usage |unit |by |unit

"Indirect |Materials"

-standard |items |and |specified |by |industry |code

EX: |rivets, |they |are |counted |by |weight



Backflushing |- |CORRECT |ANSWER✔✔-Exploding |an |end |item's |BOM |to |determine |the |
quantities |of |the |components |that |were |used |to |make |the |item |-if |you |have |2 |chairs |that |are |
done |and |you |used |40 |screws, |they |get |accounted |for |but |dont |micromanage

-when |the |order |is |finished, |it |is |put |into |the |system



2 |Types |of |Tooling |- |CORRECT |ANSWER✔✔-Standard |and |Nonstandard



Standard |Tooling |- |CORRECT |ANSWER✔✔--various |devices, |material |cutting, |and |forming |tools
|which |are |standard |in |their |size |and |capacity

, -specified |by |manufacturers |part |or |model |# |

-more |widely |available, |quicker, |more |people |can |do |it

-we |want |to |use |this |as |much |as |possible

-in |business: |lots |of |different |suppliers |and |lots |of |competition



Nonstandard |tooling |- |CORRECT |ANSWER✔✔--require |elaborate |specification

-one |of |a |king |(make |to |order)

-highly |engineered

-more |expensive |bc |custom |made

-more |time |and |more |money



Capacity |is |- |CORRECT |ANSWER✔✔-*ability |to |accomplish |something*

-the |volume |of |output |per |elapsed |time

-the |production |capability |of |a |facility

-excess |capacity |can |be |costly |and |unnecessary

-factors |that |affect |capacity: |number |of |workers, |ability |or |workers, |number |of |machines, |
waste, |scrap, |defects, |errors, |suppliers, |gov |regulations, |maintenance, |productivity



Insufficient |Capacity |can |result |in |- |CORRECT |ANSWER✔✔-Poor |delivery |performance, |increase
|in |WIP |inventory, |and |frustrates |sales |and |manufacturing |personnel




Why |is |capacity |planning |important? |- |CORRECT |ANSWER✔✔-*impacts |all |aspects |of |a |firm*:

1. |Impacts |ability |to |meet |future |demands

2. |Affects |operating |costs

3. |Major |determinant |of |initial |costs

4. |Involved |long-term |commitment

5. |Affects |competitiveness

Información del documento

Subido en
5 de enero de 2026
Número de páginas
28
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$19.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Lectphilip
4.0
(41)
Vendido
277
Seguidores
6
Artículos
26021
Última venta
1 semana hace


Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes