CORRECT ANSWERS | LATEST 2026/2027 UPDATE
GUARANTEED PASS | GRADED A+.
Earthwork has to do with the roadway in what way? - Correct
Answer-Earthwork is the excavation and placement of soils and
materials supporting the proposed roadway.
A job guide schedule is - Correct Answer-project specific
The material identification number for embankment in the
laboratory is - Correct Answer-004L
The material identification number for embankment in the field
is - Correct Answer-004F
Sampling in the field it is important to - Correct Answer-sample
each type of material and have enough for a representative
sample
,When to secure samples - Correct Answer-After material is
placed but before compaction effort is applied
Sample transmittal card the source uses what code for the jobsite
- Correct Answer-08
For material description the minimum is always - Correct
Answer-Color and texture
On sample bags be sure to put - Correct Answer-Project #
Sample #
Location
The material identification number for base is - Correct Answer-
030
PP is short for - Correct Answer-project personel
What is the document that itemizes the minimum requirements
for sampling and testing? - Correct Answer-Sampling, testing,
reporting guide
, Unit weight is - Correct Answer-the weight of a material
occupying a volume Basics covered in Level 1 - Correct
Answer-Nuclear Testing
Speedy Moisture
Report Forms
In Earthwork what is a Lot? - Correct Answer-A lot is 1 lift at
500 ft or within compacted area. Isolated compaction operations
are separate lots.
Sampling at the roadway is done for - Correct Answer-Done for
base, sub grade, and embankment.
Sampling is determined how - Correct Answer-generated with
random numbers usually by a Verification Inspector