This document contains the latest updated DBIA certification exam questions with verified correct answers, fully aligned with current Design-Build Institute of America (DBIA) principles and exam objectives. It covers all major knowledge areas including project delivery systems, design-build procurement methods, contracts and risk allocation, integrated project delivery, cost management, trend management, design commitment, quality assurance and control, dispute resolution, insurance and bonding, and legal doctrines relevant to design-build projects. The material is designed for comprehensive DBIA exam preparation and to reinforce real-world understanding of design-build best practices and decision-making.

Mostrar más Leer menos
Institución
DBIA
Grado
DBIA










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
DBIA
Grado
DBIA

Información del documento

Subido en
3 de enero de 2026
Número de páginas
17
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

DBIA TEST EXAM QUESTIONS AND CORRECT
VERIFIED ANSWERS| 2026 Updated

How team members are organized, establishes when parties engage,
determines roles of parties, and determines sequence of design, procurement,
and construction (db, cmar, dbb) - ANSWER-Project Delivery System


designer of record confirms the documents comply with the owner's project
criteria, all codes and standards; design confirmed within budget and schedule;
owner's review for compliance has been completed; changes made after this
may result in request for equitable adjustment; the owner and DB-er should
reach a consensus on this definition and when it occurs during the post-award
process - ANSWER-design commitment


identify design tasks and decisions to complete the design of the project;
decision making - how and when to make decisions; identify work flow of
design deliverables best supporting construction; optimize time for design
phase co-location; optimize opportunities for constructability reviews; the
initial prelim should be considered in the proposal - ANSWER-integrated design
work plan (IDWP)


four phases of oversight - ANSWER-pre-construction, contract, close-out, and
performance evaluation


phase which involves distribution of contract documents, confirm
subcontractor flow-down clauses, confirm incremental design packages,
confirm what constitutes design commitment, obtain performance/payment
bonds, obtain certificates of insurance, confirm attainment of permits and
access rights, issue notice to proceed, and schedule initial formal partnering
workshop - ANSWER-pre-construction

,If a change order becomes necessary in a design-build scenario, you can use
this to make sure you're paid for the additional work - ANSWER-Request for
Equitable Adjustment (REA)


formal partnering typically results in mutually developing one of 3 things -
ANSWER-charter, communications matrix, or issue resolution ladder


commitment between two or more organizations for the purpose of achieving
specific business objectives by maximizing the effectiveness of each
participant's resources - ANSWER-formal partnering


cost plus fee, lump sum/firm fixed price, and target price are this type of
incentive - ANSWER-implicit


incentive contracts (shared savings--early completion) and award fees (non-
cost performance factors) are this type of incentive. it is best practice for
owners to include this type of incentive in their design-build contracts -
ANSWER-explicit


an objective measure for evaluating a project that is easy to measure -
ANSWER-design quality


a subjective measure for evaluating a project that is hard to measure; this is
determined through the design process, not after the project is completed -
ANSWER-design value


(performance + quality) / cost - ANSWER-best value


(what you get) / (what you give) - ANSWER-value

, A process that lists the advantages of options and helps quickly identify the
options with the most advantages. This process avoids the double counting
inherent in listing pros and cons when in one option is also the con in another. -
ANSWER-Choosing by advantages (CBA)


amount of $$ added to the estimate to cover risks associated with the
unknown - ANSWER-contingency


tool used to identify, evaluate, manage, and resolve changes during design,
procurement, and construction; encourages proactive approach with the
owner to resolve any changes as design evolves; mitigates disputes before they
become bigger problems - ANSWER-trend management program


design development changes, work quantity adjustments, changes with
constructability or fabrication issues, escalation with materials, labor, or
equipment costs, labor and/or equipment productivity adjustments,
transportation and storage cost adjustments, and items that may have been
included in the scope but left out of the proposal - ANSWER-internal trends


client driven scope changes, unanticipated or changes in site conditions,
industry standard changes, permitting process changes, unanticipated
regulatory constraints, owner or agency specified changes, review board
impositions, changes associated with financial, tax, or legal issues, and force
majeure events - ANSWER-external trends


4 trend management tools - ANSWER-notice, estimate, register, log


verification that the design complies with performance requirements in the
RFP; validating operation of project systems and achievement of performance
requirements - ANSWER-substantiation
$11.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
KelvinBrooks West Virgina University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
267
Miembro desde
1 año
Número de seguidores
6
Documentos
3059
Última venta
1 día hace
Brooks

Welcome to Brooks Study guides! The place to find the best study materials for various subjects. You can be assured that you will receive only the best which will help you to ace your exams. All the materials posted are A+ Graded. Thank you very much!

4.1

31 reseñas

5
14
4
6
3
10
2
1
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes