BUS375 Exam 2 Latest 2017
Las últimas cargas en BUS375 Exam 2 Latest 2017. ¿Buscando notas en BUS375 Exam 2 Latest 2017? Tenemos muchas notas, guias de estudio y notas de estudio disponsible para tu escuela.
-
1
- 0
- 0
All courses for BUS375 Exam 2 Latest 2017
-
BUS375 Exam 2 Latest 2017 1
Últimos notas y resúmenes BUS375 Exam 2 Latest 2017
Question 1 
Which of the following will correctly calculate the total slack in an activity?
A.LS – ES
B.LF – EF
C.LS – LF
D.LF – ES
E. Both A and B are correct
Question 2 
Which of the following is provided by both the project network and the work breakdown structure?
A. Dependencies
B. Sequencing
C. Interrelationships
D. Activity duration
E. Timing
Question 3 
Which of the following is NOT one of the basic rules to follow when developing project networks?
A. An activity cannot begin unt...
- Examen
- • 7 páginas's •
-
BUS375 Exam 2 Latest 2017•BUS375 Exam 2 Latest 2017
Vista previa 1 fuera de 7 páginas
Question 1 
Which of the following will correctly calculate the total slack in an activity?
A.LS – ES
B.LF – EF
C.LS – LF
D.LF – ES
E. Both A and B are correct
Question 2 
Which of the following is provided by both the project network and the work breakdown structure?
A. Dependencies
B. Sequencing
C. Interrelationships
D. Activity duration
E. Timing
Question 3 
Which of the following is NOT one of the basic rules to follow when developing project networks?
A. An activity cannot begin unt...