EIS 3315 Chapter 7 (Motiwalla) Exam With
Complete Solutions
1) The ERP implementation phase is just after the go live phase. - ANSWER Answer: FALSE
Diff: 2 Page Ref: 191
2) A readiness assessment should be conducted before going live. - ANSWER Answer: TRUE
Diff: 1 Page Ref: 192
3) The readiness process should only include key "super" users. - ANSWER Answer: FALSE
Diff: 2 Page Ref: 192
4) The stabilization period is from the go live date to about 90 days after, or until the number
of issues to be fixed is reduced to a manageable number. - ANSWER Answer: TRUE
Diff: 2 Page Ref: 192
5) Work on the system development should continue during the stabilization period. -
ANSWER Answer: FALSE
Diff: 3 Page Ref: 192
6) Once the system is in the production phase, there is no further need for training. - ANSWER
Answer: FALSE
,Diff: 1 Page Ref: 192
7) Training should gear up during the readiness process. - ANSWER Answer: TRUE
Diff: 2 Page Ref: 192
8) The assessment of readiness should start just before the go live date. - ANSWER Answer:
FALSE
Diff: 3 Page Ref: 192
9) Elaborate readiness checkpoints help insure that the go live process is smooth. - ANSWER
Answer: TRUE
Diff: 2 Page Ref: 192
10) The readiness process will focus on assessing whether the system configuration is ready
for go live. - ANSWER Answer: FALSE
Diff: 3 Page Ref: 193
11) Everything should be completed and ready for testing at the first readiness checkpoint. -
ANSWER Answer: FALSE
Diff: 2 Page Ref: 193
12) The readiness process will clarify what needs to be done and provide more focus for the
, project team. - ANSWER Answer: TRUE
Diff: 2 Page Ref: 193
13) There should be at least three readiness reviews before the ultimate decision to go live. -
ANSWER Answer: TRUE
Diff: 3 Page Ref: 194
14) The readiness review status and the go live date should only be communicated to the
team leads. - ANSWER Answer: FALSE
Diff: 2 Page Ref: 194
15) The process for determining readiness consists of a series of meetings and discussions on
the status of each of the area tasks. - ANSWER Answer: TRUE
Diff: 2 Page Ref: 195
16) The PMO is the Project Maintenance Office. - ANSWER Answer: FALSE
Diff: 1 Page Ref: 194
17) If everything isn't ready by the first readiness assessment, the go live date should be
pushed back. - ANSWER Answer: FALSE
Diff: 3 Page Ref: 194
Complete Solutions
1) The ERP implementation phase is just after the go live phase. - ANSWER Answer: FALSE
Diff: 2 Page Ref: 191
2) A readiness assessment should be conducted before going live. - ANSWER Answer: TRUE
Diff: 1 Page Ref: 192
3) The readiness process should only include key "super" users. - ANSWER Answer: FALSE
Diff: 2 Page Ref: 192
4) The stabilization period is from the go live date to about 90 days after, or until the number
of issues to be fixed is reduced to a manageable number. - ANSWER Answer: TRUE
Diff: 2 Page Ref: 192
5) Work on the system development should continue during the stabilization period. -
ANSWER Answer: FALSE
Diff: 3 Page Ref: 192
6) Once the system is in the production phase, there is no further need for training. - ANSWER
Answer: FALSE
,Diff: 1 Page Ref: 192
7) Training should gear up during the readiness process. - ANSWER Answer: TRUE
Diff: 2 Page Ref: 192
8) The assessment of readiness should start just before the go live date. - ANSWER Answer:
FALSE
Diff: 3 Page Ref: 192
9) Elaborate readiness checkpoints help insure that the go live process is smooth. - ANSWER
Answer: TRUE
Diff: 2 Page Ref: 192
10) The readiness process will focus on assessing whether the system configuration is ready
for go live. - ANSWER Answer: FALSE
Diff: 3 Page Ref: 193
11) Everything should be completed and ready for testing at the first readiness checkpoint. -
ANSWER Answer: FALSE
Diff: 2 Page Ref: 193
12) The readiness process will clarify what needs to be done and provide more focus for the
, project team. - ANSWER Answer: TRUE
Diff: 2 Page Ref: 193
13) There should be at least three readiness reviews before the ultimate decision to go live. -
ANSWER Answer: TRUE
Diff: 3 Page Ref: 194
14) The readiness review status and the go live date should only be communicated to the
team leads. - ANSWER Answer: FALSE
Diff: 2 Page Ref: 194
15) The process for determining readiness consists of a series of meetings and discussions on
the status of each of the area tasks. - ANSWER Answer: TRUE
Diff: 2 Page Ref: 195
16) The PMO is the Project Maintenance Office. - ANSWER Answer: FALSE
Diff: 1 Page Ref: 194
17) If everything isn't ready by the first readiness assessment, the go live date should be
pushed back. - ANSWER Answer: FALSE
Diff: 3 Page Ref: 194