Answers 100% Guaranteed Pass.
Under the Contractor Quality Control (CQC) process, inspection is provided by the contractor
(T/F) - Answer✔True
Owners generally engage the services of a professional construction management firm (Agency
CM) in fast-track projects with multiple contracts. (T/F) - Answer✔True
A professional construction management firm (Agency CM) can participate in the following
phases of a project
Close out only
Construction only
conception and Design only
Conception, program planning, Design, Construction and Closeout - Answer✔Conception,
program planning, Design, Construction and Closeout
The Design-Build (DB) project delivery process may face some barriers when tried to be
implemented in the public sector. (T/F) - Answer✔true
In a project with multiple prime contractors, who is responsible for coordinating the various
trade contractors?
Subcontractors
Owner or its representative (e.g. the construction manager)
Contractor need to coordinate the work among themselves
Material Suppliers - Answer✔Owner or its representative (e.g. the construction manager)
Which of the following is under the authority of the Resident Project Representative?
To require the contractor to furnish more than that required by the plans and specifications
1|Page
, To approve materials & worksmanship that meet the contract requirements
To approve deviations from the contract requirements - Answer✔To approve materials &
worksmanship that meet the contract requirements
The Resident Project Representative should obtain the contract documents and study those as
soon as being engaged to provide resident inspection on a project. (T/F) - Answer✔True
The Resident Project Representative does not need to make any measurement for the progress
payments in the lump-sum project (T/F) - Answer✔False
When the Resident Project Representative identifies a problem with the subcontractor's work,
he/she should provide instructions directly to the subcontractor. (T/F) - Answer✔False
In a construction project, the general contractor should submit all submittals (e.g., shop
drawings, samples, etc...) directly to:
Owner's Project Manager
Design Review
Resident Project Representative - Answer✔Design Review
If the daily Construction Report is generated in the computer, it is advisable that the Resident
Project Representative prints a hard copy, signs it, and files it at the end of each business day.
(T/F) - Answer✔True
One way of making bid advertisements, as becoming more popular each day, is to post them on
the World Wide Web (internet website). (T/F) - Answer✔True
One of the items included in the Construction Diary of the Resident Project Representative is the
content of all substantive conversations held with the contractor at the site.
True
False - Answer✔True
The basic rule of contracts is that in case of ambiguity in the contract language, the intent of the
contract will generally be construed against the party who drafted the contract. (T/F) -
Answer✔True
What is the order of the sections in the three-part section format of the CSI specifications?
1) General