Unit 1 - Contract Documents and Drawings Copyright Cengage Learning. Powered by Cognero. Page 1 1. When referring to the MasterFormat® specification, which division does general electrical work fall under? a. Division 11 b. Division 23 c. Division 26 d. Division 33 ANSWER: c 2. For which type of payment agreement is a contractor required to complete a job for a fixed dollar amount, regardless of any problems that may be encountered? a. lump sum b. unit price c. cost plus fee d. net sum ANSWER: a 3. According to the simplified form of tender, how much of a tender deposit is the bidding contractor required to leave? a. $5 000 b. $6 000 c. $15 000 d. $20 000 ANSWER: d 4. Refer to the Drawing Set. Which drawing shows the electrical ratings and location of the two new transformers feeding the building? a. E2 b. E4 c. E6 d. E9 ANSWER: a 5. Refer to the Drawing Set. On which drawing can the details about the cable tray and conductor placement in the cable tray be found? a. E4 b. E6 c. E9 d. E10 ANSWER: c 6. Refer to the Drawing Set. A measurement of 50 mm is taken from drawing E3. What length does this represent in the actual building? a. 50 mm b. 500 mm c. 5 m d. 50 m ANSWER: c 7. Refer to the Drawing Set. Which drawing contains information about the building’s power distribution? a. elevation drawing b. electrical detail drawing c. lighting and power drawing d. power riser diagram ANSWER: d 8. Refer to the Drawing Set. According to the Electrical Elevations and Details Drawing E8, what is the width of MCC- 101 (as measured with a ruler)? a. 50 mm b. 100 mm c. 1 m d. 5 m ANSWER: c DOWNLOAD THE Test Bank for Electrical Wiring Industrial 7th Edition Herman Name: Class: Date: Unit 1 - Contract Documents and Drawings Copyright Cengage Learning. Powered by Cognero. Page 2 9. Which of the following are given on the site plan to indicate existing and new grading levels? a. bench marks b. contour lines c. building locations d. light standards ANSWER: b 10. Refer to the Drawing Set As given on the site plan, what is the reference point from which all elevations are located? a. bench mark b. contour line c. building location d. light standard ANSWER: a 11. Refer to the Drawing Set What does the standard format symbol consisting of two unshaded concentric circles stand for? a. fire hydrant b. gas main c. water main d. existing tree to remain ANSWER: d 12. Refer to the Drawing Set. What is the typical setpoint for the exhaust fan control circuit? a. 21°C b. 28°C c. 35°C d. 42°C ANSWER: b 13. Refer to the symbol and the Drawing Set. What does it represent in the industrial building’s drawings? a. isolation switch b. motorized damper c. unfused disconnect switch d. combination starter ANSWER: d 14. Refer to the symbol and the Drawing Set. What does it represent in the industrial building’s drawings? a. contactor b. combination magnetic starter c. switch and fuse d. fusible disconnect ANSWER: d 15. What type of drawing shows the vertical faces of a building? a. one-line diagram b. elevation c. site plan d. floor plan ANSWER: b DOWNLOAD THE Test Bank for Electrical Wiring Industrial 7th Edition Herman Name: Class: Date: Unit 1 - Contract Documents and Drawings Copyright Cengage Learning. Powered by Cognero. Page 3 16. What type of scale uses feet and inches? a. architectural b. engineering c. metric d. civil ANSWER: a 17. When pricing a job, which of these factors would be considered to adjust the standard labour units? a. number of apprentices b. job site conditions c. lengths of conductors d. number of devices ANSWER: b 18. After a contract is awarded, which document authorizes a contractor to add an extra receptacle not on the original prints? a. change order b. material take-off c. amended electrical floor plan d. job specifications ANSWER: a 19. What designation satisfies the safety standard requirements for all electrical equipment installed in Canada? a. inspected by ESA b. ULC approved c. OHSA compliant d. made in Canada ANSWER: b 20. An electrical job has been completed and has passed the final inspection. When can additional lighting circuits be added? a. when there is a new electrical permit b. when the inspector has given approval c. when there is a Request for Change Order d. any time they are required ANSWER: a 21. Briefly describe the difference between an addendum and a change order. ANSWER: An addendum is an addition or clarification issued to bidders before the bidding is closed, whereas a change order is a change made to the contract after the contract has been awarded. 22. What are shop drawings used for? ANSWER: They are provided by equipment manufacturers to show details of the equipment for a specific job. 23. Outline the steps involved when creating a job estimate. ANSWER: The main steps include preparing a material take-off, tabulating and pricing, and then summarizing the costs. Material take-offs mean counting, measuring, and listing all the material, devices, and equipment required to complete the installation and fulfill the contract. Pricing means assigning actual individual costs for each item, as well as the labour required to install everything. Standard labour units are usually used, as established by various organizations, based on specified working conditions. These units would be adjusted according to actual job conditions. Summarizing the job estimate will also include other costs, such as overhead, tool and equipment rentals, travel, and, of course, profit. DOWNLOAD THE Test Bank for Electrical Wiring Industrial 7th Edition Her

Mostrar más Leer menos
Institución
Grado











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Grado

Información del documento

Subido en
17 de noviembre de 2024
Número de páginas
105
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

,DOWNLOAD THE Test Bank for Electrical Wiring Industrial 7th Edition
Herman
Name: Class: Date:

Unit 1 - Contract Documents and Drawings
1. When referring to the MasterFormat® specification, which division does general electrical work fall under?
a. Division 11 b. Division 23
c. Division 26 d. Division 33
ANSWER: c

2. For which type of payment agreement is a contractor required to complete a job for a fixed dollar amount, regardless of
any problems that may be encountered?
a. lump sum b. unit price
c. cost plus fee d. net sum
ANSWER: a

3. According to the simplified form of tender, how much of a tender deposit is the bidding contractor required to leave?
a. $5 000 b. $6 000
c. $15 000 d. $20 000
ANSWER: d

4. Refer to the Drawing Set. Which drawing shows the electrical ratings and location of the two new transformers feeding
the building?
a. E2 b. E4
c. E6 d. E9
ANSWER: a

5. Refer to the Drawing Set. On which drawing can the details about the cable tray and conductor placement in the cable
tray be found?
a. E4 b. E6
c. E9 d. E10
ANSWER: c

6. Refer to the Drawing Set. A measurement of 50 mm is taken from drawing E3. What length does this represent in the
actual building?
a. 50 mm b. 500 mm
c. 5 m d. 50 m
ANSWER: c

7. Refer to the Drawing Set. Which drawing contains information about the building’s power distribution?
a. elevation drawing b. electrical detail drawing
c. lighting and power drawing d. power riser diagram
ANSWER: d

8. Refer to the Drawing Set. According to the Electrical Elevations and Details Drawing E8, what is the width of MCC-
101 (as measured with a ruler)?
a. 50 mm b. 100 mm
c. 1 m d. 5 m
ANSWER: c


Copyright Cengage Learning. Powered by Cognero. Page 1


mynursytest.store

,DOWNLOAD THE Test Bank for Electrical Wiring Industrial 7th Edition
Herman
Name: Class: Date:

Unit 1 - Contract Documents and Drawings
9. Which of the following are given on the site plan to indicate existing and new grading levels?
a. bench marks b. contour lines
c. building locations d. light standards
ANSWER: b

10. Refer to the Drawing Set As given on the site plan, what is the reference point from which all elevations are located?
a. bench mark b. contour line
c. building location d. light standard
ANSWER: a

11. Refer to the Drawing Set What does the standard format symbol consisting of two unshaded concentric circles stand
for?
a. fire hydrant b. gas main
c. water main d. existing tree to remain
ANSWER: d

12. Refer to the Drawing Set. What is the typical setpoint for the exhaust fan control circuit?
a. 21°C b. 28°C
c. 35°C d. 42°C
ANSWER: b

13. Refer to the symbol and the Drawing Set. What does it represent in the industrial building’s drawings?



a. isolation switch b. motorized damper
c. unfused disconnect switch d. combination starter
ANSWER: d

14. Refer to the symbol and the Drawing Set. What does it represent in the industrial building’s drawings?




a. contactor b. combination magnetic starter
c. switch and fuse d. fusible disconnect
ANSWER: d

15. What type of drawing shows the vertical faces of a building?
a. one-line diagram b. elevation
c. site plan d. floor plan
ANSWER: b
Copyright Cengage Learning. Powered by Cognero. Page 2


mynursytest.store

, DOWNLOAD THE Test Bank for Electrical Wiring Industrial 7th Edition
Herman
Name: Class: Date:

Unit 1 - Contract Documents and Drawings

16. What type of scale uses feet and inches?
a. architectural b. engineering
c. metric d. civil
ANSWER: a

17. When pricing a job, which of these factors would be considered to adjust the standard labour units?
a. number of apprentices b. job site conditions
c. lengths of conductors d. number of devices
ANSWER: b

18. After a contract is awarded, which document authorizes a contractor to add an extra receptacle not on the original
prints?
a. change order b. material take-off
c. amended electrical floor plan d. job specifications
ANSWER: a

19. What designation satisfies the safety standard requirements for all electrical equipment installed in Canada?
a. inspected by ESA b. ULC approved
c. OHSA compliant d. made in Canada
ANSWER: b

20. An electrical job has been completed and has passed the final inspection. When can additional lighting circuits be
added?
a. when there is a new electrical permit
b. when the inspector has given approval
c. when there is a Request for Change Order
d. any time they are required
ANSWER: a

21. Briefly describe the difference between an addendum and a change order.
ANSWER: An addendum is an addition or clarification issued to bidders before the bidding is closed, whereas a change
order is a change made to the contract after the contract has been awarded.

22. What are shop drawings used for?
ANSWER: They are provided by equipment manufacturers to show details of the equipment for a specific job.

23. Outline the steps involved when creating a job estimate.
ANSWER: The main steps include preparing a material take-off, tabulating and pricing, and then summarizing the costs.
Material take-offs mean counting, measuring, and listing all the material, devices, and equipment required to
complete the installation and fulfill the contract. Pricing means assigning actual individual costs for each item,
as well as the labour required to install everything. Standard labour units are usually used, as established by
various organizations, based on specified working conditions. These units would be adjusted according to
actual job conditions. Summarizing the job estimate will also include other costs, such as overhead, tool and
equipment rentals, travel, and, of course, profit.


Copyright Cengage Learning. Powered by Cognero. Page 3


mynursytest.store
13,26 €
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Reseñas de compradores verificados

Se muestran los comentarios
1 año hace

Only shows chapter 1

1 año hace

Thank you matthewbilton77 for your purchase and positive review! Wishing you all the best in your exams.

1,0

1 reseñas

5
0
4
0
3
0
2
0
1
1
Reseñas confiables sobre Stuvia

Todas las reseñas las realizan usuarios reales de Stuvia después de compras verificadas.

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
AcademicSuperScores Chamberlain College Of Nursing
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
207
Miembro desde
3 año
Número de seguidores
36
Documentos
6487
Última venta
1 día hace
AcademicSuperScores

NURSING, ECONOMICS, MATHEMATICS, BIOLOGY AND HISTORY MATERIALS. BEST TUTORING, HOMEWORK HELP, EXAMS, TESTS AND STUDY GUIDE MATERIALS WITH GUARANTEE OF A+ I am a dedicated medical practitioner with diverse knowledge in matters Nursing and Mathematics. I also have an additional knowledge in Mathematics based courses (finance and economics)

4,6

137 reseñas

5
111
4
7
3
10
2
5
1
4

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes