Question No : 1 While managing a project, you decide to create a prototype of your product first to ensure that it is acceptable to stakeholders before creating your product. This is an example of: Choice 1 Risk mitigation Choice 2 Risk avoidance Choice 3 Simulation Choice 4 Project assumptio...