Q1. Start molding specimens for strength tests within 30 minutes after fabricating
the composite sample.
A. True
B. False - Answer: B. False
ASTM C172 -Para (4.1.2) - Start molding.
specimens for strength tests within 15 min after fabricating the
composite sample.
Q2. The maximum allowable time between obtaining the first and last portions of
the composite sample may not exceed 5 minutes.
A. True
B. False - Answer: B. False
ASTM C172 - Para (4.1)- The elapsed time shall not exceed 15 min. between
obtaining the first and final portions of the composite sample.
Q3. The composite concrete sample must be protected from sun, wind,
contamination and rapid evaporation.
A. True
B. False - Answer: A. True
, ACI- Concrete Field-Testing Technician - Grade 1
ASTM C172 - Para (4.1.2)
Q4. If the concrete contains aggregates larger than those that are appropriate for
a size of mold or equipment used, the sample should be wet sieved before making
the test.
A. True
B. False - Answer: A. True
ASTM C172- Para (6.1)
Q5. The composite sample should not be remixed before beginning any tests.
A. True
B. False - Answer: B. False
ASTM C172-Para (4.1.1) -The sample shall be combined and remixed with a shovel
the minimum amount necessary to ensure uniformity and compliance with the
maximum time limits
Q6. Sampling should normally be performed, as the concrete is discharged from
the mixer.
A. True
B. False - Answer: B. False
, ACI- Concrete Field-Testing Technician - Grade 1
ASTM C172-Para (5). NOTE 2—Sampling should normally be performed as the
concrete is delivered from the mixer.
To the conveying vehicle used to transport the
concrete to the forms; however, specifications may require other points of
sampling, such as the discharge of a concrete pump.
Q7. ASTM Method C172 includes sampling from stationary mixers, paving mixers,
truck mixers, agitators, and non-agitating equipment.
A. True
B. False - Answer: A. True
ASTM C172- Para (1.1)
Q8. After sampling is completed, start the tests for slump and air content within:
A. 2 ½ minutes
B. 10 minutes
C. 15 minutes
D. None of the above - Answer: D. None of the above
ASTM C172- Para (4.1.2) Start tests for slump, temperature, and air content within
5 min after obtaining the final portion of the composite sample.